Façade cladding

Almost non-combustible ‘raincoat’ for Amersfoort city hall

Text Roel van GilsImage Tholin

Dit jaar, net voor de bouwvakvakantie, gaan de laatste HSB-elementen vanuit Holten op transport richting de bouwplaats.
Dit jaar, net voor de bouwvakvakantie, gaan de laatste HSB-elementen vanuit Holten op transport richting de bouwplaats.

Amersfoort is building a new city hall. The so-called ‘Huis voor de Stad’ will be a sustainable, open and accessible building that can be adapted to changing needs in the future. This is one reason why the design has an extensively modular and sustainable structure. The approximately 500 timber-frame façade elements have been fully prepared at Timmerfabriek Ter Harmsel and fitted with an environmentally responsible Cem-Rock Extreme ‘raincoat’ from Tholin. This sustainable, EPD/ETA-certified magnesium oxide board provides excellent wind and weather protection during construction and, with a fire rating of A1, is virtually non-combustible.

Cem-Rock Extreme forms the outer face of the timber-frame element, creating a wind- and weather-tight envelope as soon as it is lifted into place on site.

With a floor area of more than 22,000 m2 and high sustainability ambitions, the new city hall in Amersfoort is set to be a social, circular and adaptable building, according to the municipality. Its highly modular design will even allow it to be repurposed as a hotel or residential building in the future. Commissioned by Dura Vermeer, Timmerfabriek Ter Harmsel is manufacturing the approximately 500 timber-frame façade elements in controlled conditions at its workshop in Holten. In line with the project’s sustainability ambitions, the aim is to use sustainable and environmentally responsible materials wherever possible. This is also why Cem-Rock Extreme magnesium oxide board was chosen as the fire-resistant exterior finish for the timber-frame elements. 

Cem-Rock Extreme magnesium oxide board provides a fire-resistant exterior finish for the timber-frame elements.

A taste for more

Cem-Rock Extreme offers several advantages over standard cement-bonded or fibre-cement boards. It is made from natural materials, with no harmful chemicals added. Its production is also less energy-intensive. This is the first time Timmerfabriek Ter Harmsel has worked with Cem-Rock Extreme. “The product was already specified in the project documents,” says Hans Vinkers of Timmerfabriek Ter Harmsel. “The boards are very easy to work with. They don’t crumble or create dust, and they are sufficiently rigid. Compared with the fibre-cement alternatives we often use, Cem-Rock Extreme really is our preferred choice.” The board is safer to work with and, thanks to its natural raw materials, healthier too. It is also lighter than a fibre-cement alternative or a cement-bonded board.

This is the first time Timmerfabriek Ter Harmsel has worked with Cem-Rock Extreme.

Unique and coded

Timmerfabriek Ter Harmsel began producing the timber-frame elements just after the 2024 summer holidays. “The elements vary in size and in the position of the window frames. It’s a huge project, and we’re engineering everything in BIM,” explains Vinkers. “That’s no longer particularly unusual for us, as it’s now more the rule than the exception. It certainly came in handy here, given the wide variety of elements. Every element is unique and coded. In our workshop, we fitted them with aluminium window frames, glass, electrical conduit, blinds and all the other accessories. Cem-Rock Extreme forms the outer face, creating a wind- and weather-tight envelope as soon as the elements are lifted into place on site. We’ve now installed more than 2,300 m2 of Cem-Rock Extreme, and I expect we’ll reach around 2,500 m2.” The final elements will be transported from Holten to the site this year, just before the construction industry’s summer holiday.

Production at Timmerfabriek Ter Harmsel is running smoothly and remains on schedule. “As a family business, we’re used to projects of this scale,” says Vinkers. “We’re also literally and figuratively in our element when it comes to unusual shapes that others often wouldn’t dare to tackle.” The timber-frame elements will later receive an aesthetic outer skin of ceramic tiles. Huis voor de Stad is scheduled for completion in summer 2026.  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectFaçade cladding
Share this article

Advertisement

Follow Gevelbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.