From deeply profiled aluminium façades to virtually invisible window openings, the façade plays a major role in defining the architectural character of the transformation of the former mail sorting centre, The City Post in Zwolle. As the façade contractor working independently, Façadis Gevelbouw installed more than 9,000 m2 of curtain walling, including glazing, opening elements and structural provisions for the natural stone façade bands.
The transformation of the former mail sorting centre combines the existing building with new storeys. The two sections each have their own architectural character, but together form a single whole. “The façade plays a decisive role in this,” says Edwin Muller, commercial director at Façadis Gevelbouw. The company worked as an independent contractor alongside the building contractor and the services installer, directly for DC Vastgoed. “There was no main contractor overseeing all the disciplines. Each of us was responsible for our own package of work. This type of arrangement is becoming increasingly common, and we are well equipped to work in this way.”

Two building sections
The transformation was carried out in phases. Work began on the low-rise section, for which Façadis Gevelbouw received the contract in 2021. The contract for the high-rise section followed in 2024. The entire project was completed in 2025. “The low-rise section comprises six storeys, including two additional floors on top of the existing mail sorting centre,” Muller explains. “To make this extension possible, additional floors were installed in the existing building and new rooftop structures were built. The curtain wall gives this section a pronounced vertical character. Deep cover caps and aluminium fins create rhythm and texture.”

A contrasting appearance
A deliberately contrasting appearance was chosen for the extension to the low-rise section. “The gold-coloured panel finish contrasts with the façade below and makes the added storeys recognisable as a new layer in the building’s history. Here, the curtain wall features structural joints on the outside.
As a result, traditional pressure plates and cover caps are barely visible, giving the façade a clean, almost uninterrupted appearance,” says Muller. The high-rise section has a different façade design. ›
The ten storeys are predominantly articulated horizontally, giving the tower its own identity. Here too, the curtain wall system provides the basis, but the detailing and window solutions are tailored to the design of this section.
Projecting windows
Façadis installed more than 5,000 m² of curtain walling in the low-rise section and over 4,000 m² in the high-rise section. “The building envelope is made entirely of curtain walling, incorporating glazing, panels and opening windows,” Muller says. “For both sections, we used Schüco’s FWS 60 curtain wall system with neutral solar-control glazing from Polypane. In the high-rise section, some of the curtain walling uses the fire-resistant BF series. Another distinctive feature of the high-rise section is the parallel-opening window, also known as a PAF window (Parallel Ausstell Fenster). When opened, the window moves outwards parallel to the façade, leaving it clear and allowing ventilation all around. The windows are barely noticeable from the outside. The ventilation windows in the low-rise section use the Schüco AWS 70 VV.HI system.”

Unusual installation sequence
According to Muller, installing the entire building envelope was quite a challenge. “The main issue was the planned completion date. In the low-rise section, we therefore had to begin installation while the building structure was still incomplete. You can imagine that this required some coordination. The façade is not built as a standalone plane. In the end, the different sides have to meet and the building has to be enclosed all the way round. This calls for dimensional accuracy, an understanding of the progress of other disciplines and continuous coordination on site.”
In the high-rise section, the challenge lay mainly in the installation sequence. “Initially, the first five storeys could not be fitted with a façade, even though the programme called for work to start earlier. We therefore began installing the curtain wall on the fifth floor, followed by the bottom four floors. This was possible by organising the installation from inside the building. The curtain wall units were brought in through the building and pushed out from the floor slabs. They were then moved along the scaffold to their positions on the façade and installed.”

Natural stone
Less visible, but structurally important, was the integration of the many hundreds of anchor points passing through Façadis’s curtain wall to support the natural stone façade bands. “The natural stone is therefore not fixed directly to the building structure behind it, but is supported by our curtain wall, which is in turn connected to the main structural frame,” Muller explains. “The positions of the suspension points were carefully determined so that the supplier could bring the natural stone façade bands along the building by crane and hang them from the scaffold.”
The vertical accents of the low-rise section, the horizontal lines of the tower, the gold-coloured extension and the integrated natural stone bands together define the appearance of The City Post. Behind them is a single continuous building envelope by Facadis. “Everything you see is curtain walling,” Muller concludes. “A real eye-catcher in Zwolle and, above all, a project we are proud of.”
Question about this story? Ask your question
Who worked on it
The City Post in Zwolle, conversion
- zelfstandig aannemer van de gevelFaçadis Gevelbouw
- curtain wall systemSchüco
- neutrale zonwerende beglazingPolypane
Keep following this
Get an email when a new story is published. No account needed.
- ProjectThe City Post
- ThemeFacade design and construction
- SubjectVMRG
- CompanyFaçadis Gevelbouw
- CompanySchüco
- CompanyPolypane