Innovative façade system for prestigious transformation project
Text Roel van GilsImage Leebo Intelligente Bouwsystemen

Prefabricated steel frame elements create a cohesive whole
The major redevelopment of Utrecht Central Plaza at Jaarbeursplein, directly opposite Utrecht Centraal Station, is taking shape. The façades of both the existing shell and the new-build extension are being fitted with prefabricated steel frame elements from Leebo Intelligente Bouwsystemen. These lightweight façade elements combine high dimensional accuracy and excellent insulation with a high standard of quality.

Utrecht Central Plaza combines an existing building, which has been completely stripped out and is being fitted with a new façade, with a new-build extension. “The same façade system with a ceramic finish is being used for both parts, creating a cohesive whole on completion,” says Shermel Hansen of Leebo Intelligente Bouwsystemen. “The challenge was to develop a system that could be used on both structural shells: concrete in the existing building and a steel structure with hollow-core floor slabs in the new-build extension. This called for bespoke engineering and clever anchoring solutions.”
Prefabricated steel frame elements
The façades comprise fully insulated prefabricated steel frame elements. “The project includes around 400 external elements and a further 130 internal elements for the atrium,” says Hansen. “The external façade elements are storey-height, at 3.40 metres, and range in width from 7.20 metres to as much as 11 metres at the corners.” As the window frames are fitted into the façade elements at Leebo’s factory, the building is immediately enclosed with a wind- and watertight shell on site. “The external elements consist of a 200 mm steel frame filled with mineral wool, a 70 mm PIR insulation layer with a vapour-control membrane on the inside, and a 12 mm gypsum fibreboard. On the outside, a cement-bonded board is fitted with a moisture-resistant membrane. The total build-up of 290 mm delivers excellent thermal performance and structural stability,” says Hansen. The internal elements are slimmer, at 125 mm, and lighter, but follow the same principles.

Aesthetic finish
The exterior of Leebo’s steel frame façade elements is finished with special ceramic tiles from Argeton in two variants, with the ‘Toblerone’ tile as the real eye-catcher. “These tiles with a pointed profile, which are hooked onto our façade elements in prefabricated racks, create a dynamic façade,” says Hansen. Leebo also finishes the areas around the window frames and the exterior soffit. “We use Leebond aluminium composite for this, creating a sleek, durable finish.” The prefabrication approach allows the façade to be completed at pace. “The construction process works like a production line: first the steel frame elements are installed, then the ceramic tiles are hung, and finally the finishes around the window frames are fitted. The building’s appearance thus changes step by step, from the black prefabricated elements to the finished ceramic façade.”

Benefits of steel framing
According to Hansen, using steel frame elements offers significant benefits. “Compared with timber frame construction, the elements are lighter but also stronger and more dimensionally stable. What’s more, a complete prefabricated product arrives on site, including insulation, membranes, window frames and fixing points for the façade finish. This fully integrated, engineered façade system ensures consistency and quality in both production and installation.” Work is progressing steadily. While the existing building is nearly complete, the steel structure of the new-build extension continues to rise. “The result will be a cohesive whole that meets the highest technical and aesthetic standards. Our prefabricated steel frame elements provide the flexibility and efficiency needed to make challenging transformation projects like this a success,” Hansen concludes.
Een zakelijke vraag aan Leebo Intelligente Bouwsystemen? Get in touch
Who worked on Utrecht Central Plaza
- ceramic tilesArgetonIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectUtrecht Central Plaza
- ThemeFacade design and construction
- SubjectFaçade cladding
- CompanyLeebo Intelligente Bouwsystemen
- CompanyArgeton