Building as a social act

Clearing out a cupboard brought back to my attention a little gem I inherited from my father: a book with the splendid title above, written in 1960 by J.J. Vriend to mark 50 years of housebuilding by and for Philips. In his foreword, Frits Philips concludes: “And if building is a social act, building more is certainly a social necessity!” Now, 60 years after it was published, the book is still remarkably topical.
As well as building more, there is also a need for renovation, given the considerable age of many homes and the government’s drive to make them more sustainable. In this case, relations between the parties became rather less cordial when, following a smoothly run tender, they reached the final phase of the project to renovate and improve the external envelope of 96 walk-up flats with storage units.
What happened? The client and the contractor entered into a Design & Build Base Agreement (the Base Agreement), to which the UAV GC (2005) applies. The design, preparation and construction work was divided into three phases. The contract also stipulated that the contractor could only start phases 2 and 3 once it had received a written instruction from the client. Although the client intended to have the contractor carry out all the phases, if the client decided not to instruct a subsequent phase, the contractor would not be entitled to compensation or loss of profit.
When the contractor did not receive the instruction for phase 3 in time for planning purposes, a delay of around a year ensued, causing suppliers to withdraw. The contractor faced substantial price increases from its subcontractors and suppliers. It sought reimbursement of these increased costs from the client, arguing that the delay was attributable to the client. The client was unwilling to agree, as a fixed price/maximum amount had been agreed. Eventually, however, a draft instruction for phase 3 was issued. The contractor refused to accept it because it did not take account of the changes or the time that had elapsed. After discussions between the parties’ management teams, the contractor accepted the instruction, but reserved its right to an extension of time and additional payment. Even after the final instruction was issued and a new programme agreed, the parties remained divided on the matter. The contractor asked the arbitrators to make a final ruling.
The arbitrators found that the parties agreed that the instruction for phase 3 had been issued to the contractor considerably later than agreed. However, they disagreed about the causes of the delay and who should bear the resulting risks and costs. The arbitrators considered it sufficiently plausible that the maximum price had been abandoned at an early stage. In their view, the delay caused by legal proceedings brought by six tenants against the client over inadequate relocation costs was attributable to the client. However, the arbitrators considered that the contractor had not substantiated its claim sufficiently. The case documents did not make clear which facts and/or circumstances the contractor relied on in support of its arguments. In addition, the documents submitted did not provide sufficient information to estimate the amount of any damages and/or cost reimbursements. The arbitrators ruled that the contractor’s claim had to be dismissed for lack of adequate substantiation.
In this case, the difference between winning and losing was more than €735,000. Even this figure seemed to have been plucked out of thin air, after the contractor revised it downwards by €130,000. If legal proceedings prove unavoidable, make sure you are well prepared. Prefer not to rely on a Houdini act? VMRG advice is not based on illusions!