cube berlin: double-skin façade meets complex aesthetic and technical requirements

cube berlin is a striking eleven-storey office building on Washington Platz in Berlin’s Europacity district. Developed by CA Immo, the 19,000 m² building demonstrates how innovative architectural design can be successfully combined with the complex technical requirements, both structural and energy-related, of an ‘intelligent’ office building.
cube berlin was designed by 3XN Architects of Copenhagen and stands out for its fully glazed, double-skin ventilated façade, which allows the building to blend into its surroundings. The unique, bespoke façade meets not only the architect’s aesthetic aspirations but also the stringent structural and energy-performance requirements.
The combination of glass used in the fully glazed façade creates a visually striking building that reflects its surroundings on every side, changing its appearance dynamically according to the viewing angle, weather and time of day. A stepped thermal façade beneath a glass outer wall gives the dynamic building its triangular pattern. Entrances are integrated into various openings in the outer wall on all four sides of the building and across several floors.
Torben Østergaard, partner at 3XN and architect on the project: “Our original idea was to shape the building so that it would engage in a dialogue with the urban space, the surrounding buildings and the activity on Washington Platz. To make the building function as a sculpture in the square, we sought reflective glass that would emphasise the surface while also visually reflecting its surroundings.”
Another key design consideration was making optimal use of daylight for the building’s occupants. Østergaard explains: “Because the floorplates are quite deep, we wanted a fully glazed façade. This was not only to create optimal daylight conditions, but also to provide the special feeling of floor-to-ceiling windows and the magnificent views they offer.”
Energy efficient
Alongside its stunning architecture, the project stands out for its strong commitment to sustainability, with lower energy consumption than traditional office buildings. The ventilated double-skin façade played a crucial role. It provides daylight while also effectively protecting against solar heat gain and offering the benefit of natural ventilation. As Joachim Fauth of Drees & Sommer, façade consultant on the project, explains: “To prevent overheating in the cavity, we used solar-control coatings and sunlight-absorbing PVB interlayers in the outer wall.”
Matthias Schmidt, Head of Development at investor CA Immo: “We are aiming for DGNB Gold certification for this project. The façade has an extremely energy-efficient design. Together with a smart technical concept that recovers energy from heat, among other things, it contributes to an effective energy solution that challenges the prevailing idea that glass buildings are real energy guzzlers.”
Another challenge was the structural build-up of the glass. An additional interlayer had to be incorporated, and it needed to be compatible with the sunlight-absorbing PVB interlayer. National approval for this brand-new solution had to be obtained during the design and construction phases. The additional structural interlayer increased edge stability and reduced the risk of delamination, while also lowering the yellowness index.
Joachim Fauth: “Designing such a complex product requires real teamwork. And that is exactly what happened during the design phase: the glass supplier, the PVB supplier, the architect and the façade expert worked closely together.”
Expert advice and technical support
In addition to supplying coated glass products, the Guardian Glass team also provided invaluable technical expertise.
In the words of Olivier Beier Costa, who was involved in the project as Sales Manager at Guardian Glass: “The biggest challenge was bringing two things together: first, the architect’s design and aesthetic concept, and second, the building’s technical requirements. We therefore had to find products suitable for this application. This involved carrying out various tests and calculations and producing a large number of samples.”