De bestaande constructie van het glasdak was niet watervoerend genoeg en bestond uit verticale en horizontale regels, waar het water achter bleef staan.
De bestaande constructie van het glasdak was niet watervoerend genoeg en bestond uit verticale en horizontale regels, waar het water achter bleef staan.

The Willemswerf office building on the Boompjes in Rotterdam was built in the 1980s on a narrow strip of land along the Nieuwe Maas. Designed by Wim Quist, it is characterised by a diagonal bend in the façade, ‘topped off’ with a sloping glass roof measuring no less than 60 metres in length. Thirty years on, the current owner decided it was high time for a thorough renovation of the interior. Kingspan Light + Air was tasked with finally fitting the ‘glass waterfall’ with a new, watertight system.

Willemswerf is anything but modest in scale. The building is almost 100 metres long, 90 metres high and has a unique fifth façade in the form of a glass roof. Michel Verwaal, commercial director at Kingspan Light + Air, has worked in glass roofs and glass structures for virtually his entire career. In the 1980s, he prepared the estimate for Willemswerf’s sloping glass roof. “Unfortunately, we didn’t get the contract to build it at the time,” he says. “The roof has had a lot of problems with leaks, too… So the extensive renovation was an opportunity to make it watertight.”

Kingspan Light + Air carried out the glass roof renovation from March to November 2021, in the midst of the coronavirus pandemic.

Triple-barrier system

In 2020, main contractor JP van Eesteren approached Kingspan Light + Air to help develop a solution for renovating the sloping roof, together with façade consultant IBS Consultants. “The roof descends around 60 metres in a funnel shape. It is 8 metres wide at the top and just 1.5 metres at the bottom. So during a downpour, an enormous amount of water runs over the roof, including water from the façade,” Verwaal explains. “The existing structure could not drain enough water and consisted of vertical and horizontal mullions, behind which water collected. This made the structure particularly prone to leaks. IBS Consultants then took the lead in developing an alternative design, the triple-barrier system. The first barrier is an extra-wide glazing bar with double rubber seals on either side of the glass. The glass is then structurally sealed around its perimeter, forming a second barrier. Should any water nevertheless get into the system, it is channelled away from each floor section on both the left and right into the gutters, forming the third barrier.”

Thanks to a triple-barrier system, the ‘glass waterfall’ is finally watertight.

Specially adapted BA profile system

So much for the theory. The next challenge was to put it into practice at height, right beside one of Rotterdam’s main traffic arteries. “Using a tower crane wasn’t an option,” says Verwaal. “We came up with a method of bringing a scaffold from the inside to the outside on each floor, after two panes per floor had been dismantled by rope access technicians. The existing profile system was then partially dismantled, modified in specific areas and fitted with a specially adapted Brakel BA profile system and new solar-control glazing. The method had been thoroughly tested in advance using a full-size mock-up.” 

Kingspan Light + Air carried out the glass roof renovation from March to November 2021, in the midst of the coronavirus pandemic. “In the Netherlands, construction work could continue, but people weren’t allowed to go to the office,” says Verwaal. “The building was almost empty. That brought some advantages for us. For example, we were able to transport the 399 panes upstairs relatively easily using the passenger lift.” 

Thirty years on, Willemswerf has a new glass roof fitted with the unique triple-barrier system. Even Wim Quist, who died this year at the age of 91 and remained closely involved in the renovation, was able to admire the finished result. Renovation and transformation projects of this kind are a regular part of Kingspan Light + Air’s work. “There is a clear trend towards bringing existing glass roofs and structures up to today’s standards,” says Verwaal. “We have already replaced the glass roof above the atrium at the Jan van der Ploeghuis in Rotterdam, and are now working on the Van Gendthallen in Amsterdam, which has more than 9,000 m2 of glass structures.”  

Question about this story? Ask your question

Who worked on it

Willemswerf in Rotterdam

  1. main contractorJP van Eesteren
  2. geveladviseurIBS Consultants
  3. BA-profielsysteemBrakel

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectWillemswerf
  • SubjectGeneral
  • CompanyJP van Eesteren
  • CompanyIBS Consultants
  • CompanyBrakel
Share this article

Advertisement

Follow Gevelbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.