Interchangeable façade for a circular security checkpoint
Text Roel van GilsImage SFS, IV Totaalbouw

Work is currently nearing completion on a new security checkpoint at Schiphol, where security staff check people
and vehicles. What makes this project unique is that it is being built using materials recovered from the demolition of three office buildings and three cargo buildings at the airport. The façade cladding, by contrast, is new, but here too sustainability and circularity have been prioritised, thanks to SFS’s concealed mechanical NV3 fixing system.

IV Totaalbouw installed the façade finish on the new security checkpoint for main contractor BAM. “We specialise in a wide range of construction work at airports,” says Ivan Oostra of IV Totaalbouw. “In this case, we were responsible for installing around 400 m2 of Rockpanel façade cladding on a timber-frame substructure. The specification already called for SFS’s concealed mechanical NV3 fixing system. It was our first experience with both the system and SFS, and one we would certainly be happy to repeat.” Ivan particularly praises SFS’s involvement, and especially that of Gijs Gooren. “He was always on hand with advice and open to feedback.”
Plug and play
The NV3 system was supplied virtually plug and play. “We shared the contractor’s drawings with SFS, which then carried out the wind load calculations and determined the fixing pattern for the panels accordingly. The entire package was sent to the CNC router,” Ivan explains. “For us, it was simply a matter of installing and aligning the aluminium support rails, onto which we could easily hang and secure the panels. It works really well.” The mechanical fixing means the NV3 system allows the façade panels to be replaced at a later date or reused in their entirety, including the profiles. Circularity at its best! Another advantage of SFS is that it is a guaranteed, tested façade system. The combination of the NV3 fixing system and Rockpanel has its own unique ETA certification. “And that is a major benefit, especially in the complex environments where we work.”

The next project at Schiphol is already in the pipeline. “Another new building, with exactly the same finish, is going up right next to this security checkpoint. We will of course also install SFS’s concealed mechanical NV3 fixing system there.”
Een zakelijke vraag aan SFS Group the Netherlands B.V.? Get in touch
Who worked on it
Doorlaatpost Schiphol
- main contractorBAM
- façade finishingIV Totaalbouw
Keep following this
Get an email when a new story is published. No account needed.
- ProjectDoorlaatpost Schiphol
- ThemeFacade design and construction
- SubjectFaçade cladding
- CompanyBAM
- CompanyIV Totaalbouw
- CompanySFS Group the Netherlands B.V.