Logistical challenge during renovation of occupied Multi Trade Centrum

Logistical challenge during renovation of occupied Multi Trade Centrum

A special project: the renovation of Multi Trade Centrum on Willem de Zwijgerlaan in Amsterdam. MVDS Architecture, based in Amsterdam, designed the building’s entire new façade. The interior was also refurbished. Keeping the businesses in the building, including a hotel, open throughout the works presented challenges. J.P. van Eesteren was the main contractor for the project. Hermeta supplied the stylish black window frames, complete with glazing featuring Wiener Sprossen.

The glazing features glazing bars for an authentic appearance.

A logistical challenge

Sander Spoor, project manager at J.P. van Eesteren: “The distinctive aspects of this project were the logistics and collaboration. Multi Trade Centrum on Willem de Zwijgerlaan houses a hotel, office units and a gym, all of which remained open during the renovation. This was made possible by taking various measures, such as installing dust screens around the work areas. The old façade was then demolished in sections and a new one installed. We soon settled on Hermeta for the window frames. We have worked together on several projects, and the experience has been excellent. Hermeta is a company that not only delivers, but also contributes ideas, including at the pre-construction stage.”

The building houses a hotel, among other businesses, which remained open during the renovation.

Ready-to-install window frames

Peter van der Sloot, work planner at Hermeta: “For this project, we worked closely with the timber-frame supplier, Timmerfabriek A. Gerritzen in Nijmegen.   

We first manufactured the window frames at our factory. The stylish frames and glazing were then fitted into the timber-frame elements at Gerritzen’s factory. We fitted the glazing with glazing bars and a French balcony to create an authentic appearance. The French windows extend from ceiling to floor, allowing plenty of natural light into the building. As the windows can open fully, we installed glass balcony balustrades on the outside for safety.”

The logistics chain must work

Van der Sloot: “Thanks to our close collaboration, we were able to supply the contractor with ready-to-install window frames, fully sealed.” Spoor adds: “This collaboration also made us much more efficient. We didn’t need any extra cranes, and we were able to make the entire building wind- and watertight within a few months. Keeping commitments and trust are important parts of how we work together. The logistics chain has to work. That went very well with Hermeta on this project.” 

The rear of the building overlooks a harbour. The French windows extend from ceiling to floor, allowing plenty of natural light into the building. (Image: Wim Burgwal)

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeExtending the life of existing facades
  • SubjectGeneral
Share this article

Advertisement

Follow Gevelbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.