Underground problems

A harmonious start to cooperation between the parties to a construction project does not guarantee that they will reach the finish line unscathed.
Disputes regularly arise over the quality of the work and/or defects, which unfortunately sometimes lead to a full-blown battle over who is responsible for these shortcomings. Even when an arbitrator has ruled on a dispute between the parties several times, interim relief proceedings may still be needed to calm things down again.
For years, the dank recesses of the basement of a restored bank building, converted into a home and office, were the battleground on which a client and a contractor played the leading roles. What was the problem?
The dispute between the parties stemmed from an additional instruction given to the contractor during the renovation works to install a swimming pool in the basement. After handover, it became clear that the water was not confined to the pool. After numerous investigation reports, the conclusion was that the leaks observed had arisen mainly because of defects where the new concrete basement roof joined the (newly rebuilt) basement walls. At the client’s request, the arbitrator went down to inspect the basement and, having considered all the circumstances, ruled that the contractor had failed to fulfil its obligation to deliver a watertight basement. The contractor was ordered to carry out repairs, with a penalty of €1,000 per day up to a maximum of €50,000. After the initial ruling and the repairs subsequently carried out by the contractor, it was the contractor who applied to the arbitrator. He claimed that he had fulfilled his repair obligation under the earlier ruling and demanded repayment of the penalties imposed, which the client had, in his view, unlawfully allowed the bailiff to collect. The client, however, again demanded repairs because leaks were still occurring. The contractor was once more ruled against and again ordered to carry out repairs, this time with a new penalty. The contractor considered appealing. But before an appeal was lodged, the parties were back in court, this time in interim relief proceedings. The contractor said that he had carried out as much investigation as possible to identify leaks that might be visible from the outside, but had found nothing and left without achieving anything. The client had refused access to the basement to both the contractor and staff from the investigation firm he had engaged. The contractor argued that access was essential to repair the leaks. The client confirmed that access had been refused, explaining that he did not want to grant access until he had received a plan of action. The contractor maintained that a plan of action could only be drawn up once he had been able to inspect the inside. If his application for access could not be granted, he sought to be released from his repair obligations under Article 6:60 of the Dutch Civil Code (creditor default).
The arbitrator agreed with the contractor that access to the inside of the basement was essential to repair the leak. By refusing access, the client was making it impossible for the contractor to fulfil its repair obligations. The arbitrator therefore ruled that the contractor’s repair obligations would be suspended for as long as the contractor was denied access to the basement.
The contractor (the debtor) had been ordered to carry out repairs but was unable to fulfil its obligation because of the client (the creditor). The statutory provision on creditor default invoked by the contractor states that, if the creditor is in default, the court or arbitrator may, at the debtor’s request, rule that the debtor is released from its obligation to perform.
Although the contractor got the better of the client in the interim relief proceedings, working together and keeping the lines of communication open is generally the best way to avoid sinking or swimming. In this case, creditor default was ‘below ground’, but it can also occur above ground level. Want to keep your knowledge of metal windows and façade elements up to date? The VMRG Quality Requirements and Recommendations are available at https://vmrg.nl/kwaliteitseisen/kwaliteitseisen-en-adviezen.