Masterpiece: Mr Bettina Hertstein | A fire flares up

The agreements are clearly documented. The subcontractor accepted the contractor’s General Terms and Conditions and signed the subcontract at the designated place. The subcontractor also agreed to the Fire Safety Basis of Design (‘the UPD’). In the distribution centre to be built by the contractor, the subcontractor will install the CO2 fire protection system in accordance with the contractor’s deadlines and sequence of works. But before handover, ‘a small fire broke out’!
How did that happen? The contractor postponed the subcontractor’s start date twice, then issued a revised schedule more than three months after the second postponement. A further three months later, the contractor proposed a new 19-week programme for the subcontractor’s works. The subcontractor did not consider 19 weeks feasible and proposed 26 weeks from week 40 (early October 2023), but with a ‘reservation’ due to the room integrity tests, which could take an additional four days. Inspection could only take place once everything was complete. The subcontractor actually started in week 40. At the end of November, it sent a schedule for the interim inspection, final inspection, test discharge and completion of outstanding items/reinspection. But then there was an unexpected fire to put out: the plans for the schedule had to be thrown out yet again. The contractor’s client had decided that it wanted a greater stacking height in the distribution centre, making modifications to the fire safety system necessary. When the contractor asked the subcontractor whether its additional works could be completed by the end of March (2024), including approval and certification, the subcontractor said that handover on 31 March would only be possible “if absolutely nothing went wrong”. It sent details of the additional works and schedule (“subject to the availability of the various parties”), together with the associated costs, to the contractor in an email on 31 January and a quotation on 19 February. The contractor subsequently drew up the additional agreements in ‘the Addendum’, which the subcontractor then signed. The fire was quickly brought under control with the right firefighting equipment. Yet it took only a fresh spark to turn the parties’ intended handover at the end of March into a raging inferno.
When the contractor requested the handover file and certificate earlier than the subcontractor considered appropriate, the subcontractor replied that it would send the handover file after connecting the remote monitoring signals, and provide the certificate once “everything was complete”. On 26 and 28 March, the inspection body rejected the system, notifying the contractor on 2 April. The inspection body sent the list of outstanding items to the subcontractor on 4 April. The subcontractor undertook to rectify the items at its own expense by 10 April at the latest. Following a further inspection, the system was approved on 12 April. Certification was available on 19 April, allowing the system to be formally handed over. The contractor said this was too late, particularly because its client had threatened to serve a notice of default and impose a penalty, which it intended to pass on to the subcontractor. It therefore ‘set off’ just over €116,000 against the invoice submitted by the subcontractor on 3 April, claiming this amount as damages for the late handover.
The subcontractor flew into a rage and turned to arbitrators from the Council of Arbitration in Construction Disputes, asking them to put out the now raging fire. They had faced hotter situations and kept their cool. The subcontractor claimed, among other things, the amount the contractor had withheld. The contractor argued that, due to the loss it had suffered as a result of the late handover, it was also claiming repayment of the portion of the subcontractor’s invoice it had already paid. The parties disputed each other’s claims.
The arbitrators saw through all the smokescreens. They had the right tools for the job. They considered the handover date: had it been imposed by the contractor, as the contractor argued, or proposed, as the subcontractor maintained? The contractor’s question about ‘whether handover by the end of March was possible’, the subcontractor’s extensive reservation and the substantial additional work all indicated that the date had not been imposed, but was a target date. Moreover, the inspection report of 28 March showed that most of the items preventing approval of the system concerned work that the contractor still had to carry out. The contractor lost the case and had to pay the subcontractor. Fire put out.
Want to know more about the (fire) safety of VMRG metal windows and façade elements? They must comply with the fire safety requirements set out in the VMRG Quality Requirements and Recommendations.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeSafe and verifiable facade construction
- SubjectVMRG