A stormy relationship

When a collaboration gets off to a sunny start but is unexpectedly enveloped in dense fog, disputes over alleged defects can keep the relationship going for longer than originally intended. Strong gusts of wind and driving rain do nothing to improve matters.
As part of the refurbishment of an apartment block, a contractor and a façade contractor entered into an agreement for the supply and installation of façade units. The window frames were to be manufactured under warranty and had to comply with NEN 2778 for Wind Zone II, coastal area up to 15 m high, ≥ 300 Pascal. A number of apartments developed leakage problems soon after installation. For this reason, the contractor withheld the final instalment. Despite the façade contractor adjusting the window frames several times, the leaks persisted, by then also affecting the sliding door to a penthouse. Soon afterwards, the relationship between the parties was at risk of reaching code orange, and the façade contractor was served with a notice of default. As the contractor believed that the façade contractor was taking too long to carry out repairs, they appointed an expert. The expert recommended various modifications and advised replacing the window frames with frames featuring a heavier profile if they still failed to perform adequately after testing.
The solution seems acceptable to both parties until the contractor states that the façade contractor must carry out repairs in accordance with the expert’s report, while the façade contractor argues that the contractor is only entitled to the level of wind and watertightness contractually agreed under NEN 2778. A period of calm then follows, until the contractor sends the façade contractor a letter containing a declaration of conversion. It states that the façade contractor no longer needs to carry out repairs. Instead, the contractor seeks substitute damages. Although the façade contractor offers to carry out repairs at the eleventh hour, the contractor does not take up the offer. The contractor has the leaking façade units and window frames replaced by a third party. The expert’s report also indicates that some of the façade units need to be replaced with units featuring heavier profiles. The arbitrator is asked to calm the brewing storm.
In addition to substitute damages, the contractor claims the replacement of some of the façade units with units featuring heavier profiles. The façade contractor mounts a detailed defence. In its view, heavier profiles would amount to a retrospective tightening of the specification requirements, which cannot be held against it. It claims payment of the final instalment. The arbitrator finds that, under NEN 2778, a ‘Wind Zone II, coastal area up to 15 m high’ requires a test pressure of ≥ 300 Pascal, as also set out in the agreement. The expert’s report does not in itself establish that the façade units are of insufficient quality. The façade contractor acknowledged that, to meet the agreed standard, six tilt-and-turn windows needed additional fastening (locking cams), and the sliding door required reinforcement profiles. This establishes the façade contractor’s liability for this failure. In the arbitrator’s view, the façade contractor was given sufficient time to carry out repairs. As the façade contractor failed to repair the defects in time, the contractor was entitled to convert its claim for repairs into a claim for substitute damages.
To determine the amount of damages payable, the arbitrator compares the actual situation with the situation that would have existed if the agreement had been performed correctly. The need to replace the façade units with higher-quality units has not been established. In the arbitrator’s view, the necessary repairs were limited to fitting locking cams to the tilt-and-turn windows and installing reinforcement profiles in the sliding door, including levelling the subframe retrospectively. The contractor’s claim for costs of € 90,000 is not eligible for reimbursement without further explanation. The final instalment due to the façade contractor remains unpaid and has not been disputed by the contractor. The arbitrator considers only the necessary repairs to constitute damage. As the contractor has been largely unsuccessful, it is also ordered to pay the legal costs. Rather than receiving the amount claimed, the contractor must pay approximately € 10,000 after the damages awarded for the established failures have been set off against the outstanding final instalment.
The arbitrator’s ruling has cleared the air between the parties. Don’t want to be caught out by a bolt from the blue? Consult Kwaliteitseisen en Adviezen (vmrg.nl) 2022 for the latest information from VMRG on metal windows and façade elements. Then you’ll always have an umbrella to hand!