BIM, more time for the beautiful

On 14 March 2022, VMRG held an online expert session on BIM. The guests were experts Chris Schoneveld, BIM coordinator at Alkondor Hengelo, and Pim van Meer, BIM manager at developer and builder VORM. They answered the questions below, among others.
What exactly does BIM stand for?
Chris Schoneveld: “The term ‘BIM’ encompasses three meanings:
1. ‘Building Information Model’: the digital representation of a building’s functional and technical characteristics, which serves as the starting point for and supports activities and decision-making throughout the building’s life cycle;
2. ‘Building Information Modelling’: the process of digitally modelling a building and working (together) using digital building models;
3. ‘Building Information Management’: the creation, management and (re)use of digital building information throughout the building’s life cycle.

How does a BIM model get started?
Pim van Meer: “The consultants (architect, structural engineer, building services consultant) create a performance model. This sets out the spatial allowances required by subcontractors and manufacturing partners. Ideally, the spatial allowances should all be agreed before the building permit application is submitted, and before the contractors and suppliers start modelling. Once the contractor takes over as part of the design and build team, they will have engaged the right subcontractors and suppliers. They can then check whether the spatial allowances included in the model are correct.”
What about interim 2D output?
Pim van Meer: “2D output should be generated (semi-)automatically from the BIM models. But really, you should avoid this. It is better to teach everyone in the supply chain to view the models. That is the whole point of BIM: the models are always up to date.”
What about spatial allowances in a performance model?
Chris Schoneveld: “If you know in advance, as a façade contractor, the parameters defining the space you have to work in, things become much easier. By the time engineering starts, there are no more structural issues to resolve. You can see that the construction process then runs much more smoothly too.”
How do you incorporate a specification into a model?
Pim van Meer: “I’m not a fan of specifications. If there is a discrepancy between the model and the specification, someone has a big problem. That’s why you want a single source of truth, and that is the model. Only the general section of the specification cannot be incorporated into the model; the rest poses no problem.”
What do façade contractors receive from the consultants?
Chris Schoneveld: “We receive 3D models from the building services and structural consultants. From all the other consultants, we generally receive only reports, for example on fire resistance and energy performance requirements. Sometimes you find that things contradict each other, which can affect the model and even the design, and you want to avoid that.”
What is the contractor’s role at this stage?
Pim van Meer: “In my view, the contractor should be involved as early as possible in the process as the building consultant, taking the lead and coordinating, in other words, asking the right questions of the right parties. I say ‘in my view’ deliberately, because BIM is about working as a team, and in some places procurement still holds sway.”
Do you do the modelling yourselves? How does that work?
Chris Schoneveld: “Yes, we do our own modelling. We recently started using Orgadata’s Logikal production preparation software, which is linked to Revit. Logikal generates a 3D model, which we then place back into the BIM model. We also use Logikal to control the machines. The first projects using the Logikal link have now been completed. This makes it easier for companies to move from a traditional process to a BIM process than it was in previous years.”
Is reducing failure costs still the best argument for BIM?
Pim van Meer: “I prefer to call it ‘More time for the beautiful’. If we automate everything we can and make everything we can more efficient, we have more time for the beautiful. You can tell project managers, the kings of the clash model: ‘Would you like less hassle and more time to work out the project-specific details? You can have that. Everyone needs to review things earlier; we build it digitally before we build it for real.’”
The VMRG BIM working group has developed a BIM protocol, a BIM execution plan and an ILS Gevel. These are intended to channel information, prevent information overload and clarify which party receives which information. They can be found on the VMRG website: www.vmrg.nl/Kennis/VMRG-en-BIM.