Demonstrable quality assurance will be of great value when the Building Quality Assurance Act comes into force

The Building Quality Assurance Act (Wkb) will come into force in 2022.
The main aim of this Act is to reduce errors and improve quality. It will bring significant changes to the construction industry, particularly in the preparation and execution of projects.
Building Quality Assurance Act
The aim of the Building Quality Assurance Act is to reduce defects in construction. The government therefore wants construction companies to carry out better quality checks on their work. Under the Act, quality assurance means monitoring the quality of the design and construction to ensure that the finished building complies with the requirements of the Building Decree, which will be renamed the ‘Decree on Buildings and the Living Environment (Bbl)’ when the Environment and Planning Act comes into force. Under the current system, the local authority checks building plans in advance and supervises construction to ensure it is carried out in accordance with the permit granted. Under the Wkb, construction industry parties themselves are responsible for ensuring compliance with the requirements, using a quality assurance instrument applied by an independent quality assurer. The practical implications of the new Act are explained in 4 steps in the construction process.
Step 0: Environmental permit
As soon as an initiator, client or contractor intends to build, an environmental permit must be applied for. The applicant submits a spatial design with the application. This enables the local authority to understand the intended use and appearance of the building, and to assess the application against the local authority’s environmental plan and the risks associated with the location.
Step 1: Quality check of the building plan
Once the environmental permit has been granted, the activities covered by the Building Quality Assurance Act begin. The first step is for the designer and contractor to draw up a building plan. This sets out what will be built and how it will meet the technical requirements, which are derived from the Building Decree. The plan also includes a quality assurance plan, setting out the risks identified by the parties involved and how they will be managed. The quality assurer checks the building plan and quality assurance plan and, after any necessary amendments, approves the complete package. The quality assurer examines how the contractor has organised its own quality assurance. They assess how risks are managed and decide what to inspect on site and how often. Before construction begins, the local authority is notified that the work will be carried out in accordance with the building plan. The quality assurance plan is submitted with the notification, along with details of the quality assurer and the quality assurance instrument to be used. The local authority does not assess the building plan at this stage.
Step 2: Quality checks during construction
During construction, the contractor gathers all the evidence, such as subcontractors’ certificates and additional process checks, for example in the form of photographs, to demonstrate compliance with the technical requirements, and compiles a file. The quality assurer checks that the contractor is compiling the file properly and carries out spot checks to verify that all elements are being constructed in compliance with the technical requirements. The foundations, walls and floors are all checked, as are the façades, windows and doors.
Step 3: Submission of the file
If everything has been carried out correctly and the quality assurer is satisfied, they issue a declaration confirming that all requirements have been met. This declaration is submitted to the local authority together with the file. The file records the as-built condition of the building and also explains how the risks were managed. Once the file is complete, the building may be occupied 10 working days after the completion notification has been submitted to the local authority. The building’s user also receives a so-called ‘Consumer File’.

Changes across the construction supply chain
The changes apply to everyone building a structure covered by the Building Decree, such as a house, office or bridge. They will affect every sector of the construction industry. The following overview shows the main differences in a traditional construction process, from design to handover, for a typical project using metal windows, doors and façades.
Demonstrating quality will become even more important
The biggest change for the façade sector is the need to demonstrate quality during design and construction. The quality assurer will want to see that the building meets all the requirements. How will the contractor demonstrate this to the quality assurer? By delivering verifiable quality and compiling a file containing the supporting evidence. During the design phase, this will generally include certificates and test results demonstrating that the selected façade system can meet the requirements of the Decree on Buildings and the Living Environment (or Building Decree). Correct manufacturing and installation are therefore vital. Demonstrable quality during manufacture and installation will consequently be valuable when compiling the file. If manufacturers and installation companies in the façade sector hold the appropriate quality marks and certificates, this will help the contractor convince the quality assurer that the statutory requirements have been met.
In conclusion
The introduction of the Building Quality Assurance Act will bring major changes. The most important is that contractors will have to demonstrate compliance with the requirements by compiling a file. This will involve documenting a great deal, and a quality assurer will visit the site to check that everything is being carried out in accordance with the rules. Critical elements are also likely to be tested more often in advance, helping to avoid difficult disputes later on as far as possible. The aim is for owners to receive buildings that demonstrably comply with the rules and provide the quality they have paid for.