Earthquake-resistant Forum Groningen

At the heart of Groningen’s city centre, Forum Groningen has risen over the past few years, an imposing building with major (and international) ambitions. The structural challenges were immense: the columns do not align on any floor and the façades are inclined. The building also complies with the Dutch Practical Guideline (NPR) for earthquake-resistant construction. It called for engineering at the very limits. On every level.
With its public opening on 29 November 2019, Forum Groningen reached the culmination of an intensive 12-year process. Designed by NL Architects, the building has 17,000 m² of floor space across ten storeys and is open seven days a week, from early morning until late at night. Beneath the building is a car park for 374 cars and a bicycle parking facility for 1,200 bicycles. Forum houses five cinema screens, a multifunctional event space and the city library, and hosts international exhibitions. The building also contains many open areas that are free to access, with comfortable seating areas, study and work spaces, and meeting rooms. There are also several food and drink outlets, with the highlight being Groningen’s highest rooftop terrace, at a height of 45 metres, which can also host a rooftop cinema and offers wonderful views over the city.

Whiplash effect
De Groot & Visser was brought in at an early stage by both the contractor BAM Bouw en Techniek regio Noord and structural engineer ABT to contribute to the façade concept. “The challenges lay both in connecting the curtain wall to the natural stone and in meeting the earthquake-resistance requirements,” begins Anco Bakker of De Groot & Visser. “The latter was also a relatively new phenomenon for us at the time. Our preferred supplier Schüco did have an earthquake-resistant profile system in its range, but it did not meet the requirements specified here. The NPR is based on a short but extremely powerful seismic wave caused by gas extraction and the subsidence of the ground. This differs from the longer wave that is usually expected. When an earthquake sets the building in motion, it moves from side to side. This so-called ‘whiplash effect’ formed the basis of the calculation method we used to design the façade.”
Unitised curtain wall
When engineering Forum’s façade system, De Groot & Visser therefore had to account for the forces generated by an earthquake, in addition to the usual wind load and dead load. “This produced extreme values,” says Bakker. “We opted for a unitised curtain wall, with the units hung with greater-than-usual clearance between them. We normally allow for a gap of 10 millimetres between units; here, a 30-millimetre vertical joint was used. The idea is that if the building shakes during an earthquake, the units will not collide. The horizontal joint was also made wide, allowing for possible movement of the floors and supporting structure to prevent damage and dangerous situations in and around the building. The glass is bonded into the curtain wall profiles rather than retained in a rebate. The bonded construction also improves safety and is better able to absorb shocks.”

3D engineering
As if that were not enough, the units are also diamond-shaped. “None of them is quite square,” says Bakker. “Some also slope backwards. Because every unit is unique and the building is so technically challenging, we engineered the entire project in a 3D environment. Two mock-ups were then made: one of the ‘standard’ unitised curtain wall and one of the backward-sloping section, for water-tightness testing. It was a very nerve-racking process. In the end, we were able to identify and eliminate all the imperfections and critical points. Everything was incorporated into the 3D model, which we then used to control production. We set up a special area in our production facility where the glass could be bonded to the profiles under controlled conditions.”
Steel internal screens
The interior of Forum Groningen is enhanced by a large number of steel internal screens and lift screens, more than 80% of which serve as fire barriers. MHB was responsible for engineering, supplying and installing more than 1,400 m2 of steel-framed glazed lift screens, clad doors, double-action doors and screens with structural glazing, all in steel. “The biggest challenge was installing the lift screens, particularly the structural glazing,” recalls Arijan de Jong of MHB. “The lift screens are full storey height and each is around 10 metres long. The glass is structurally bonded on the lift shaft side. Since the lift could not be used during construction, platforms were installed in the lift shaft so that the glass could be bonded in place. A striking detail is that the lift control buttons are integrated into the glass.”

Fire-resistance requirements
The steel screens and pivot doors on the upper floors also serve as fire and smoke barriers. De Jong: “Groninger Forum was the first building for which compliance with the new standard NEN 6075 (Determination of resistance to smoke permeation between rooms) was set as an additional requirement. This was in anticipation of the new Building Works and Living Environment Decree (BBL). Since there are quite a few pivot doors, this proved quite a challenge. Working with consultancy DGMR, we were able to demonstrate that we met the specified fire-resistance and smoke-control requirements. Following an intensive engineering project with BAM Bouw en Techniek regio Noord, using BIM, the screens were manufactured at our factory. On site, internal transport proved a daunting task because of the size of the screens and the lack of handling equipment. The contractor’s support teams used temporary ramps to move the screens to the correct floors.”
Late last year, Forum Groningen opened with a spectacular sound and light show. Since then, residents and visitors to the city have had access to a multifunctional centre. “A project the whole of Groningen is proud of,” concludes Bakker.
Question about this story? Ask your question
Who worked on Forum Groningen
- architectNL ArchitectsIn this story
- contractorBAM Bouw en Techniek regio NoordIn this story
- structural engineerABTIn this story
- facade systemDe Groot & VisserIn this story
- steel interior and lift enclosuresMHBIn this story
- consultancyDGMRIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectForum Groningen
- SubjectVMRG
- CompanyNL Architects
- CompanyBAM Bouw en Techniek regio Noord
- CompanyABT
- CompanyDe Groot & Visser
- CompanyMHB