Façade contractor as a participant in the project team

A new model agreement for collaboration in a project team has recently been introduced. Until now, the VGBouw Model from 1992 had been used. That model has proved successful and has led to few disputes. So why introduce a new model project team agreement?
The VGBouw Model project team agreement
In the project team as we have known it for decades, the client, design consultants and contractors work together on the design. The design consultants work under the consultancy terms and conditions De Nieuwe Regeling 2011 (DNR 2011). Early in the design phase, the contractor contributes its construction expertise and cost knowledge. This input can help optimise the design. Other specialists, such as a façade contractor and/or an installer, may also be asked to contribute their specialist knowledge to the design. Subcontracts between the main contractor and the façade contractor often contain no provision covering the façade contractor’s rights and obligations in relation to its design input in the project team. Sometimes they state that the façade contractor is expected to accompany the contractor to meetings with the client whenever the contractor considers this necessary. This is based on a kind of ‘gentlemen’s agreement’. Another complicating factor is that a subcontract may have a title, such as ‘project team agreement’ or ‘co-making agreement’, that does not correspond to its contents. If the options provided by the VGBouw Model for participation in the project team by specialists in fields other than that of the main contractor were actually followed in practice, the roles of all parties would generally be set out more clearly in legal terms. In return for the contractor’s design input, the contractor receives a special reward: it is entitled to be the first and only candidate to realise the design, provided that agreement on the price is reached in accordance with the project team agreement. For the execution of the project, a construction contract is concluded with the contractor alongside the project team agreement, with the Uniform Administrative Conditions 2012 (UAV 2012) applying to it.
Liability of the project team contractor
The contractor’s active involvement in developing the design does not automatically make it liable for errors in its design proposals. The VGBouw Model reflects an important ruling by the Arbitration Board for the Building Industry from 1982. In that ruling, the Board held that not every project team participant is partly liable for errors made through joint consultation; each party is liable for errors made within its specific area of expertise. It is also relevant that the designer has accepted the contractor’s advice and adopted it as its own. The duty to warn also applies between parties in a project team.
The new Model project team agreement DG 2020
A new model for a project team agreement had been under discussion for years, for several reasons. One was that some construction and infrastructure parties wanted to use an integrated contract form for project delivery, with design and construction under one contract, rather than the ‘traditional’ form with design (DNR 2011) and construction (UAV 2012) under separate contracts: the Uniform Administrative Conditions for Integrated Contracts 2005 (UAV-GC 2005, soon to be UAV-GC 2020). The VGBouw project team agreement is specifically intended for use during the design phase preceding the construction phase under UAV 2012. Five authors with different areas of expertise in construction and infrastructure, together with Duurzaam Gebouwd, have taken up the challenge of drawing up a new project team model. In addition to the traditional project team option, the new Model Agreement for the project team DG 2020 includes an option to proceed, following the joint development of a (partial) design in the project team, under the integrated UAV-GC contract form.
Façade contractor as a participant in the project team
The new Model is based on the contractual relationship between the client and the contractor. The contractor can engage its subcontractors and suppliers to participate in the project team. It must pass on the relevant provisions of its own agreement with the client, as far as possible, to the contracts it enters into with its subcontractors.

Attitude and conduct
The new Model also addresses the attitude and conduct of the parties. It goes so far as to set out the competencies and qualifications required by the client of people representing their organisations as project team participants. The aim is therefore to achieve not only an optimised design, but also effective collaboration. One way to support collaboration is to ensure that each project team participant can inspect the agreed obligations of the others. Such transparency will certainly influence how people behave.
Liability of the project team contractor acting as an adviser
What stands out in particular is that the contractor’s liability for its advice in the project team is subject to the limited liability regime for advisers under DNR 2011. This puts its liability on the same footing as that of the designer/adviser governed by DNR 2011. The contractor’s liability for advice given to the designer and accepted and adopted by the designer as its own is otherwise dealt with in line with the VGBouw Model.
Design fee for the contractor and façade contractor participant
The new Model includes a clear provision on payment for design advice from the contractor and participants representing the contractor. The client pays the contractor for its participation in the project team and for the participation of those representing it, at hourly rates to be agreed separately, plus reimbursement of any further cost items to be specified. There is therefore more to discuss than the relevant provisions the contractor passes on in the subcontract. Is this the end of the gentlemen’s agreement for the façade contractor? I think so. Review the project team contracts with the contractor, check whether they are based on the UAV (old or new model) or the UAV-GC, and negotiate payment for design work and advice.
The new Model project team agreement can be downloaded free of charge from the Duurzaam Gebouwd website.
Mr Bettina Hertstein, www.bouwrechtbedrijf.nl