For the sake of the case

CASE STUDY BY MR BETTINA HERTSTEIN
Poor communication does not just regularly lead to relationships breaking down in private life. The same applies to business relationships. When a difference of opinion turns into accusations about the other party’s alleged shortcomings, it is important not to dismiss those accusations as hot air. But when payment is also overdue, the prospects for continuing the relationship are put at risk.
It all started so well. A contractor built a commercial premises for a client. The construction went according to plan and in a spirit of cooperation. Both parties also approved the outstanding handover items that the contractor still had to rectify in the handover report. Yet things went wrong.
The client served notice of default on the contractor for failing to rectify the handover items properly. The contractor demanded payment of its outstanding invoices and brought proceedings before the Arbitration Board for the Building Industry. The contractor’s solicitor disputed the claims made in the notice of default. In a response to the contractor’s solicitor about the outstanding invoices, the client’s solicitor said that the ‘miscellaneous’ item on the variation invoice had been almost entirely invented and had apparently been drawn up ‘pour besoin de la cause’. Despite the provocative statements, the parties reached an amicable settlement with full and final discharge after several rounds of negotiations. For a moment, it seemed that the Arbitration Board would not need to take action.
A year later, things were once again at risk of going wrong when the client discovered a leak in the roof around a rooflight. After the client reported it, the contractor carried out repair work and the leak stopped. However, six months later, the client reported further problems, this time with draughts inside and around the building. The client commissioned a building survey and a thermographic survey. The surveying firm concluded that the draughts were caused by air leakage combined with various defects in the thermal insulation of the building envelope. On the basis of the defects in workmanship identified in the report, the client ordered the contractor to rectify them within six weeks. The contractor’s solicitor replied that the demand for repairs would not be met.
The client brought proceedings before the Arbitration Board. The client argued that the building was difficult to heat and lost heat quickly because of air leakage combined with defects in the insulation of the external envelope. The client sought repairs to the airtightness and thermal insulation, as well as compensation for the water damage caused by the roof leak. The contractor disputed these claims, referring to the settlement agreement concluded between the parties. As regards the leak, the contractor referred to an investigation it had commissioned, which concluded that the leak was not attributable to it. The contractor also disputed the amount of compensation claimed.
The arbitrator did not need to be taken aback when he first considered the case. The correspondence submitted showed that the settlement agreement covered all points in dispute, including any defects that might subsequently be identified by thermographic survey. In the arbitrator’s view, the contractor was entitled to rely on the full and final discharge covering defects relating to airtightness and insulation. He therefore dismissed the claims for repairs. The arbitrator made an exception for the repairs to the thermal insulation and vapour barrier around the roof penetrations, which the contractor had offered to carry out as a goodwill gesture at the hearing. On the basis of that undertaking, he ordered the contractor to carry out these repairs. As regards the consequential loss caused by the leak, the arbitrator considered that the contractor had provided sufficient evidence that the leak was not attributable to it. The claim for consequential loss was dismissed.
Both parties did their best to get the case back on track, but there was too much hot air between their positions for them to get closer without further investigations and arbitration. Experts in airtight metal windows and façade elements, take a look at the VMRG!