Getting the measure right makes all the difference

Mr. Bettina Hertstein www.bouwrechtbedrijf.nl
Mr. Bettina Hertstein www.bouwrechtbedrijf.nl

Putting everything down in the contract as clearly as possible does not ‘automatically’ mean that the parties will achieve the intended end goal of their collaboration in harmony. It is important to respect each other’s legitimate interests, but also to ‘get’ what you agreed. In the property developer’s view, that did not happen. He considers the performance of his façade panel manufacturer and supplier to have fallen far short, and he is not letting the matter drop.

In July 2018, the parties entered into an agreement for the replacement of the external façade of a shopping centre. The property developer wanted the façade work to be carried out in several phases. To keep the cost of the sheet material at the price level then in force, production was to be carried out under a single order and in a continuous production run. The project got off to a smooth start, but setbacks followed. These included the bankruptcy of Contractor 1, the developer’s installation contractor, and complications caused by the COVID-19 pandemic. In November 2020, more than two years after the project began, the supplier delivered its last batch of façade panels. In early 2021, the developer introduced a new contractor to the supplier. The new contractor said that the next phase would be carried out in the fourth quarter of 2021. At its request, the supplier sent a net panel schedule. This showed that, of the 1,375 m2 net of panels ordered, 736 m2 net had been produced and delivered.

Then ‘all was quiet on the other side’ for more than a year, until the supplier suddenly received questions from the developer, including about the gross quantity held in storage and whether any had already been cut to size. The supplier was taken aback. It had lost a great deal of money following the bankruptcy of Contractor 1 and, after the developer had previously mentioned two or three possible replacement installation contractors, it had heard nothing more. The supplier replied that only a few sheets remained on its premises, and that they were not in a condition worth writing home about. If the developer still wanted to complete the project using its sheet material, the supplier would submit a new quotation at current prices, as four years had passed since the agreement was signed.

The developer had had enough. In March 2023, he escalated the matter and, through his lawyer, said that he had decided not to use the supplier’s panels on the façade sections. He demanded that the supplier deliver the remaining gross quantity of panels produced and paid for. He had ordered all the material at once and paid in full. In his view, the supplier was in breach of contract. He had therefore rightly terminated the agreement and wanted his money back for the panels not yet received. After an unsuccessful attempt to obtain a favourable ruling in the district court, he appealed to the Court of Appeal. The supplier argued that it had fulfilled its contractual obligations and had produced and delivered what it could based on the information provided by the developer. After all these years, the gross cladding panels could no longer be supplied, and the remaining stock had been cleared away. The developer had failed, since November 2020, to provide the necessary dimensions. The supplier had indicated that it was willing to produce the panels after all, subject to a price increase and receipt of the dimensions. The developer did not take up that offer.

The Court of Appeal found, on the basis of the parties’ submissions, that the developer should have known that the gross panels would only be produced once he had supplied the dimensions. The supplier’s uncontested submission was that the raw materials purchased for the panels in 2018/2019 had become unusable over time. The developer could not reasonably expect to be supplied with gross panels at the original 2018 price. This also follows from Article 7.1 of the VMRG Terms and Conditions, which also addresses the sharp rise in raw material prices. The developer’s appeal was unsuccessful. The Court of Appeal upheld the district court’s judgment.

Being ‘on good terms’ may be asking a little too much in business. Still, you can make all the difference by keeping to the agreed dimensions, knowing and honouring the terms of your agreements. Visit www.vmrg.nl to find out all about metal windows and façade elements.

‎‎

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectVMRG
Share this article

Advertisement

Follow Gevelbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.