Grunting on the factory floor

(Re)building often means clients eagerly anticipating the ‘dream’ end result. For contractors, it is often not just about keeping to a tight schedule, but also about having a passion for creating something beautiful. The completion is usually celebrated in style by everyone involved. Years after the party bunting from the completion celebration had been packed away, defects were found, in the client’s view, in his business premises. Legal limitation periods did little to improve his mood.
The client instructed his contractor to build a new business hall on an existing concrete floor in a former pigsty, and to remove and replace the roofing on an existing business hall. The construction contract was concluded under the General Conditions for Construction Contracts in the Construction Industry 1992 (AVA 1992).
All was well until, several years after completion, the client claimed that cracks had appeared in the concrete floor of the new business hall and that the roofs of both business halls were leaking. The contractor dismissed the client’s claims about cracks in the floor. He disputed the allegation that he had driven heavy machinery over it. Moreover, the cracks could have been caused by the demolition contractor hired by the client to demolish the old pigsty. The client also claimed that the steel and roof structures had a serious defect. Continuing to trade arguments over who was right seemed unlikely to lead to a solution. The arbitration tribunal of the Raad (van Arbitrage in bouwgeschillen) had to assess the parties’ grunting against the legal rules and the terms of their contract.
The arbitrator had the unenviable task of sifting through the parties’ claims and denials. First, he considered the completion date, taking into account the facts and circumstances. He established that the work was deemed completed at the end of 2016. The AVA provide for a 30-day maintenance period, meaning that it lasted until 31 January 2017 at the latest. After that, the contractor could be held liable for ‘ordinary’ latent defects for a period of five years. A period of ten years applies to serious defects that affect the stability of the structure. The client brought the dispute before the Raad on 9 September 2022, well after the five-year limitation period had expired, but within the ten-year period.
As regards the cracks in the floor, the parties agreed that the pigsty had been demolished by a third party engaged by the client. Since the client had not substantiated his claim that the contractor caused the cracks, it had not been established that the contractor was responsible. The arbitrator dismissed the client’s claims on this point.
The client claimed that the deformation of the steel structure and the leak in the roof structure constituted a serious defect. The contractor relied on the five-year limitation period for latent defects. In his view, there was no serious defect. To assess the matter, the arbitrator inspected both business halls. As regards the deformation, the parties agreed that the bracing behind the supporting beam had not been properly tensioned throughout. As regards the leak, the arbitrator observed no signs of leakage. He found that in both buildings the ridge pieces did not fit together properly, meaning the ridge could not be watertight. He concluded that the stability of the business halls, or of any essential part of them, was not at risk, and therefore there was no serious defect. On this point, the arbitrator declared the client’s claims inadmissible. There is no room for snoozing when limitation periods are at stake. They are only overridden in very exceptional cases.
Building with metal window frames and façade elements? You don’t have to roll around in the mud to feel good. VMRG members are ready to help and look forward to welcoming you.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- SubjectVMRG