Leiden’s new gateway

The station district in Leiden is undergoing a major transformation. Work is well underway to turn this centrally located area into a vibrant destination where people can enjoy living, working, shopping and spending time.
The ambitions are clear: the aim is to make this the most sustainable kilometre in the Netherlands. BREEAM Very Good-certified Lorentz serves as a new gateway of sorts, connecting the station with the old town centre.

Lorentz has a total floor area of approximately 50,000 m2. Designed by Neutelings Riedijk Architects, it comprises a dark-coloured podium with commercial space, a car park and Leiden’s largest cycle parking facility. Two towers containing 167 rental apartments sit above the podium. Phase 1 saw the completion of the podium and two residential towers. Phase 2 is due to start later this year and involves the construction of an office tower. Every effort was made to deliver a high-quality façade for phase 1.
A clear dimensional system
Together with Neutelings Riedijk Architects, the ABT team faced the challenge of achieving the highest possible quality on a tight budget.
“Drawing on our experience and collaboration with the architect, we were approached by the Van Wijnen / Hurks construction consortium (BCL) to develop the final design into a construction design and provide BIM coordination support,” says Matthijs Gerds of ABT. “This is a commercial development where the budget was a key consideration. The biggest challenge was to bring the quality of a commercial building into a residential project. We succeeded. Not by devising exceptional solutions, but by taking a smart, pragmatic approach to developing the construction design. We created an integrated detail using existing techniques and suppliers’ expertise. The very precise design by Neutelings Riedijk Architects, with its clear dimensional system, also played a crucial role. It helped us enormously, and proved valuable well into the construction phase.”

Three distinct elements
The Lorentz building comprises three different façade elements. “The podium is constructed from precast concrete and partly brickwork, while the towers are clad in aluminium standing seam panels,” Gerds continues. “Each of these three ‘elements’ called for a different approach. We developed them over time in the 3D model. We aimed to make the construction process as efficient as possible and leave the specialist knowledge where it belongs: with the various suppliers. For example, we did not model the window frame profiles, but paid close attention to the design and positioning of the subframes. This meant the window frames could be modelled very simply using standard solutions. The same applied to the precast concrete elements and the brickwork in the podium. On the towers, the dimensions of the standing seam panels were key. We modelled every panel in detail in the Revit model, resulting in straightforward installation and, ultimately, a very clean appearance.”

Curtain walling and window systems
The entire Lorentz building features Kawneer AA 100 aluminium curtain walling and RT72 Reflex window systems, also by Kawneer. “The project came to us thanks to previous positive experiences with main contractor Van Wijnen,” says Leon Wolters, director of asw gevelbouw, who was responsible for all the window frames and curtain walling in the building. “The challenge was clear from the outset: the budget was the deciding factor in whether the building could be delivered. It was a constant ‘battle’ with the schedule, logistics and prices. Acting as a construction partner helped us achieve the result. Technically, it was not rocket science, partly thanks to the precise design.” Jaco van der Ham of Kawneer adds: “Extra attention was given to drainage at the long vertical window strips. A large volume of water has to be drained across a relatively narrow width, so extra drainage holes were integrated into the profile. Concealed hardware was also used because of the limited space at the sides.” All the window frames and glazed screens were prepared and manufactured at asw’s production facility in Weert. Wolters says: “On site, they were delivered just in time and installed straight away. Space on the construction site was very limited. Even so, we installed around 5,000 m2 of window frames and curtain walling in a short space of time.”

“We achieved a high standard of aesthetics on a low budget,” Gerds concludes. “This was partly thanks to our pragmatic approach to developing the design from final design to construction design. The construction design identified the critical points and set out the interfaces with suppliers. Our focus was always on ‘how do you make something, what does the construction process look like, and what do you actually need?’ We took that approach into the construction phase, ensuring that the 3D model matched the realities of the site as closely as possible. This unquestionably leads to a higher-quality end result, and the project was also a turning point for us. We are now much more inclined to think critically in advance about how BIM can support construction,” Gerds says. Meanwhile, an agreement has also been signed for the development of phase 2: construction of the third tower, intended for office use.
Project details
Lorentz, Leiden
Client/investor
is SAREF (Syntrus Achmea RE&F)
Contractor:
BCL (Hurks+Van Wijnen)
Architect:
Neutelings Riedijk Architects
Façade contractor:
asw gevelbouw
Engineering:
ABT
System supplier:
Kawneer