Locked out

Mr. Bettina Hertstein www.bouwrechtbedrijf.nl
Mr. Bettina Hertstein www.bouwrechtbedrijf.nl

A key often plays a ‘key role’ in someone’s life. The key to someone’s heart, or to a home, usually brings joy. Losing a key is frustrating until we find the key to the solution. A key also represents security. After all, if it has a high security rating, we hope the criminals will move on to the next street. Handing over the keys to a building project involves numerous legal considerations. One client realised this rather late.

To build his new home, the client entered into a construction contract with the contractor. Work got off to a good start but, as so often happens, the problems came at the end. When the house was ready for handover, the client was still not ready to pay the outstanding invoices. The contractor’s reminders made no difference. The client had left a substantial part of the contract sum unpaid. The variation for an extension with foundations was also still outstanding. The contractor therefore called off the handover. The construction fencing around the house remained in place, and the client was not given a key to the property. The contractor exercised its right of retention. It put A4 sheets on all the windows stating that the construction company was exercising this right. The client was not pleased. Twice, he vandalised the construction fencing, had it removed and threw it onto a large pile. He also had the cylinders drilled out of the front door and removed the notices of the right of retention from the fencing and windows. Two days after the first ‘break-in’, the contractor reasserted its right of retention, retaking physical control of the house. The following day, the client damaged another section of fencing and had the cylinders drilled out. The client then handed his keys over to the contractor, which replaced the fencing and cylinders once again. The contractor also arranged for CCTV surveillance. However, the outstanding invoices remained unpaid.

One fence led to another when the contractor took the client to court. The court heard that the client had failed to pay more than € 200,000 of the contract sum, as well as the additional work he had commissioned for an extension with foundations. When the contractor explained at the hearing that the client had signed the variation quotations, the client replied that he did not know whether the signatures on them were his and would need to check his email. The court did not consider this a clear denial and concluded that the quotations had been signed, particularly since the client did not dispute that the additional work had in fact been carried out. As for the client’s actions in gaining access to the house, he believed he was entitled to do so ‘because it was his own home’. The judge swiftly dismissed the client’s claim that he did not know the contractor was entitled to exercise a right of retention. In addition to emails about this, signs had been put up on the fencing and A4 sheets had been placed on all the house’s windows, stating that the construction company was exercising its right of retention. The court agreed with the contractor that the client had acted unlawfully. Among other things, the client was ordered to pay the unpaid invoices, plus contractual interest of 6% from their due dates. He also had to pay damages for the cost of CCTV surveillance.

The handover of the work could be suspended until the client had paid. This is permitted if all the requirements for exercising a right of retention are met: 1) the contractor must have physical control of the property (the work), 2) it must be clear to third parties that the contractor has control of the work, and 3) the claim must be due and payable. For a subcontractor, exercising a right of retention is rarely an option because it does not have physical control of the property, for example, by being the only party with a key to the site. Not every client is the same, and sometimes you just get unlucky.

Want to avoid getting into a fix? Check with VMRG members! The door is open for a good conversation about metal windows and façade elements. And a cup of coffee!

‎‎

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectVMRG
Share this article

Advertisement

Follow Gevelbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.