Across the North Sea, an almost Shakespearean drama is unfolding. Betrayal, infidelity and intrigue take centre stage. The Speaker of the House is now famous around the world for his “Order, order”, calling the “honourable members” to order and reason. A similar keeper of order would be welcome on many a construction site. In the absence of one, an arbitrator was asked in summary proceedings to step in and calm things down.

What was going on? The clients claim that, in addition to delays to the construction schedule and various outstanding works, the contractor is wrongly refusing to allow specialist contractors onto the site. As a result, construction and finishing work have been virtually at a standstill for several months. The parties entered into a building contract for the construction of the shell of a house. The UAV 2012 applies, and the design and specifications were prepared by the practice acting as the clients’ contract administrator. The clients also included a provision in the building contract, albeit subject to reservation, stating that they might enter into a further agreement with the contractor for the finishing work. They later decided to engage specialist contractors for the finishing work.

At the contractor’s invitation, the shell works were inspected twice in the presence of the contract administrator. The contractor then sent an invoice for additional work and the 6th and 7th stage-payment invoices, including the final payment due on completion. The clients claim that the works have not yet been handed over because 20 of the 33 outstanding items have not been rectified. They also claim that the contractor caused delays to the construction schedule and seek an advance payment on account of the deduction. They have left the invoices unpaid. The contractor then exercised a right of retention over the site and removed the specialist contractors engaged by the clients to carry out the finishing work. After the 6th stage-payment invoice was paid, the contractor relinquished its right of retention but still did not allow the finishing contractors onto the site. The contractor disputes that handover has not taken place and that it caused any delay. Neither the clients’ demands that the contractor allow the finishing contractors onto the site nor the parties’ attempts to reach an amicable agreement have resolved the matter.

Based in part on its inspection of the shell works, the arbitrator considers that the 20 outstanding items, or even all 33 items identified at the first inspection, are not of such a nature as to prevent handover. Moreover, the clients did not give written notice within eight days that the works had not been approved. The works are therefore deemed to have been approved and handed over. The delay to the construction schedule attributable to the contractor is limited, partly because handover was found to have taken place at an earlier date. The amount of the deduction is too small to award to the clients as an advance under interim relief proceedings, and the claim is therefore dismissed.

Regardless of whether the contractor was entitled to refuse access to the finishing contractors, it was contractually obliged to allow specialist contractors onto the site, as it had always done before. This was important to the contractor itself, not least because progress on some of its own work depended on the finishing specialist contractors completing their work.

The arbitrator orders the contractor, within two working days of service of the judgment, to grant all finishing contractors nominated by the clients full and unrestricted access to the site, subject to a penalty payment.

For the avoidance of doubt: the VMRG is pushing boundaries without a “backstop”. And there is no need to choose “deal or no deal”!  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectVMRG
Share this article

Advertisement

Follow Gevelbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.