Masterpiece by Ms Bettina Hertstein | Whodunit

Construction disputes are sometimes like detective stories, gripping right up to the end, when the culprit is revealed. Usually, the most unlikely suspect did it. Fortunately, construction cases rarely involve a culprit being led away in handcuffs, but they do raise the question of who should bear the cost of the damage. And that can make for a gripping conclusion.
The main contractor entered into a subcontract with the subcontractor for the design, engineering, construction and installation of façade and roof elements for a project awarded to the main contractor. The main contractor made the UAV-GC 2005 Conditions applicable to its agreement with the subcontractor. In addition to the UAV-GC, it also made its general subcontracting conditions applicable. After completion, the main contractor claimed almost €250,000, excluding VAT, from the subcontractor for delay damages and other costs. The subcontractor disagreed, and when the main contractor threatened to pin these costs on him, he called in the arbitrators to do some proper detective work.
It is undisputed that the main contractor drafted the agreement with the subcontractor. On the cover page, the parties are referred to as ‘contractor’ and ‘subcontractor’. Elsewhere in the agreement, the terms ‘client’ and ‘contractor’ are used exclusively, but the provisions make clear that these refer to the main contractor and the subcontractor. The agreement stipulated that, in accordance with the UAV-GC, the contractor must complete the work by 1 May 2016 so that it is ready for acceptance by the client. This milestone date was designated as the contractual completion date. The agreement also stipulated that, if the 1 May 2016 milestone date was missed, the penalty would equal the costs actually incurred.
The subcontractor completed the work for the main contractor well before 1 May 2016. The main contractor does not dispute this. The main contractor completed the overall project for its client on 27 June 2016. If the main contractor had wanted to specify that the subcontractor had to complete its work for the main contractor at an earlier date, so that the main contractor could complete the work for its own client before 1 May 2016, it should also have included other milestones in the agreement with the subcontractor, together with penalties for missing them. It did not do so. The milestones it had in mind are not binding deadlines for the subcontractor unless they are set out in the contract.
The main contractor also claimed to have incurred additional costs because it had to intervene repeatedly in the design and construction work that the subcontractor was required to carry out under the UAV-GC. In its view, the subcontractor had acted more like a traditional UAV 2012 subcontractor. The subcontractor argued that its work followed from the main contractor’s design and build contract with its client, and that it had carried out only the usual engineering work. The arbitrators found that both parties had worked in a more traditional way than the UAV-GC agreement on paper required. The work was carried out on the basis of a design produced by the main contractor, with detailed engineering by the subcontractor. In view of the above, the arbitrators concluded that the main contractor was not entitled to compensation for the claimed delay damages and other costs.
The main contractor did it. The subcontractor was cleared. On any computer, it is easy to cut and paste text. In the days before computers, this was called making a patchwork. Make sure your contract is not a scrapbook or a lucky-dip surprise, and that you do not fall victim to unwelcome surprises. Do not let your cut-and-paste job prove fatal. A contract tailored to your metal windows and façade elements is based on the VMRG Conditions!