No active memory of

Things do not always go as expected. Usually, this means that something has gone wrong. In such cases, it is helpful if the parties remember what they agreed and have had the foresight to put it in writing. The client and the main contractor had no trouble remembering. It was the subcontractor whose memory was rusty. Perhaps it was no coincidence that the defects identified by the client were precisely the subcontractor’s responsibility.
The main contractor was contracted by the client to renovate the client’s home. The work included replacing the old steel façade elements, doors and windows with frames, with new steel façade elements. This part of the work was carried out by a subcontractor engaged by the main contractor.
No one had forgotten the start date, and the work was also completed on time. However, at handover, and again a month later after the subcontractor had been given a second chance, the client still found rust spots on the frames. When the client found further rust spots a year later, following another repair, the main contractor held the subcontractor liable and asked him for a new plan of action. According to the client, the only proper repair method was to remove the façade elements, treat them elsewhere in accordance with the prescribed method and then reinstall them. The main contractor informed the subcontractor of this and said that the costs should be borne by him. The subcontractor eventually engaged a sub-subcontractor to carry out local repairs once again. This again failed to achieve the desired result: rust was subsequently found not only in several new locations, but also on the façade elements that had been repaired locally. The subcontractor then failed to provide a new plan. The subcontractor and his sub-subcontractor denied any further liability for the alleged defects.
At the client’s request, following an earlier investigation by SKG-IKOB, COT conducted an investigation that included an indicative acid test (effervescence test) using a hydrochloric acid solution. COT concluded that no zinc coating had been applied to the steel façade elements before they were painted. The main contractor then held the subcontractor liable for the missing zinc coating and ordered him to replace the façade elements within three months. The subcontractor refused.
Six years after handover, the parties met before the Arbitration Board for Construction Disputes. In a letter sent before the hearing, the subcontractor said he did not remember signing a copy of the subcontract with the main contractor. The main contractor pointed out that both parties had signed the agreement, both had acted in accordance with it, and the subcontractor had even referred to it in his invoices. The Board ruled on the main claim between the client and the main contractor, and on the indemnity claim between the main contractor and his subcontractor. The main contractor sought an order requiring the subcontractor to pay whatever the main contractor was ordered to pay in his dealings with the client. The client sought an order requiring the main contractor to replace, at no cost, all the installed steel façade elements with new, identical, sound steel galvanised and coated façade elements of the Janisol Arte brand, using a third party affiliated with VMRG. The client also sought payment for consequential losses and expert costs. The main contractor argued that he had not failed to fulfil his agreement with the client because he had instructed the subcontractor to galvanise the façade elements. The arbitrators considered that, although the defect was hidden and could not have been detected at handover without destructive testing, the main contractor was in principle liable for hidden defects. They also criticised the main contractor for failing to carry out a lasting repair for years, thereby underestimating the seriousness of the matter and forcing the client to commission investigations by third parties. The main contractor was ordered to carry out the repairs and pay the consequential losses and investigation costs claimed by the client. The subcontractor’s defences in the indemnity proceedings were unsuccessful. It was established that he had forgotten to apply the agreed zinc coating, or had failed to apply it. On this basis, the subcontractor was ordered to pay whatever the main contractor was ordered to pay the client.
This is a case none of the parties involved will soon forget. A useful reminder: if you want sound steel façade elements, you know to turn to VMRG members!