MASTERPIECE: MR BETTINA HERTSTEIN

When tempers flare between parties, things can quickly come to a head. If the genie then refuses to go back into the bottle, they usually find themselves having to call in outside help. It need not be supernatural. The honour fell to the arbitration tribunal of the Council of Arbitration in Construction Disputes to assess the cracks in their relationship from both a construction and legal perspective.

What happened?

Back in 2016, the client entered into a building contract with the contractor (or its predecessor in title) for the installation of new aluminium window frames and panes in a building in which he rents out several flats. In 2018, a pane broke in one of those flats. The contractor did not leave the client in the lurch. It investigated the matter and established that the pane had been incorrectly installed. Under warranty, and in accordance with the applicable VMRG Conditions, it replaced the pane with one of the same quality standard. It inspected all the other panes it had supplied and installed. They were all found to be in order. The tension that had arisen between the parties had thus dissipated. But not for long.

According to the client, panes also broke in two other flats in 2019. In 2022, he formally served notice of default on the contractor and demanded that it replace the panes. The contractor consistently denied liability and rejected the notice of default. It did not comply with the demand. The client had a third party replace the panes that had spontaneously broken in the two other flats. He believes the contractor should bear the cost. The contractor, however, takes a very different view. 

The dispute came to a head in the hot summer of 2023, when the client brought the case before the Council. At the hearing, he stated that his glazier, who had replaced the two panes, had observed that “the screws were a little too close to the glass”. However, the glazier was unwilling to give evidence, and no photographs were taken during the replacement work. The client believes that, although thermal breakage, which is excluded from the warranty under the VMRG Conditions, was not in his view the cause, the cause of the cracks makes no difference to the contractor’s liability. He seeks compensation for losses already incurred and those yet to be incurred, in view of the risk of further spontaneous breakage. The contractor contests, with reasoned arguments, all the client’s assertions and claims.

In the arbitrator’s view, the client had in no way demonstrated that the contractor had failed to fulfil its contractual obligations. Without further substantiation, such as photographs taken while the panes were being replaced or an expert report, the arbitrator could not accept the client’s argument that the contractor was liable regardless of the cause of the breakage. The costs therefore remain at the client’s own risk and expense. The arbitrator is also no longer able to examine the panes originally installed. The fact that one pane was replaced because of installation defects does not mean that the other panes were also incorrectly installed. The client did not dispute the contractor’s assertion that it had inspected the other panes at the time. Nor does the cracking pattern of the original panes, as shown in photographs submitted by the client, reveal the cause of the breakage. The photographs also do not show conclusively that the breakage was thermal. At the hearing, the contractor further explained that the mullions and transoms of the panes with cracks shown in the photographs were not fitted with screws. Incorrectly positioned screws therefore cannot have been the cause. Nor was it established that the panes were unsuitable for their intended use: the two panes replaced by the client’s glazier were replaced with panes of the same quality, and they have still not developed any cracks or breaks. The same is true of the first pane replaced by the contractor. The client’s claims are dismissed.

The realities of construction can once again prove challenging. Although VMRG members do not have a crystal ball, they do stand behind their quality. The client therefore need not fear that the panes will spontaneously crack in future.

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectVMRG
Share this article

Advertisement

Follow Gevelbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.