Point of no return?

For negotiations to succeed, at least two parties need to want to move forward together. One makes an offer, the other accepts it. This means there is agreement between the parties and the contract is concluded. But if one of the parties lacks the intention to proceed, no contract is formed. The ‘spurned’ prospective partner can be deeply frustrated. Just how serious the matter was for a client and a contractor became clear when they faced each other not once, but twice, before the ‘Arbitration Board for the Construction Industry’.
As is usually the case, the parties get off to a good start. The client invites the contractor to participate in a construction team, where, in short, the contractor contributes cost expertise and construction know-how to the design. Under the construction team agreement, the contractor is entitled to be the first and only candidate to submit a price offer to carry out the works. If the client is satisfied with the offer, a construction contract can be concluded between the client and the contractor.
Things do not go as either party expected. After numerous emails back and forth and, eventually, the inevitable registered letters, relations are far from cordial. The client believes the total amount in the contractor’s draft estimate is more than €1 million higher than agreed by the construction team. That is precisely why, according to the contractor, the construction team agreement was terminated by operation of law, as provided for in a clause in the agreement. It states: “This agreement shall terminate, without the need for judicial or arbitral intervention, if the tender exceeds the client’s estimate (…).” The client’s legal counsel believes that the clause in question was included solely to protect the client and that the contractor cannot rely on it. Unsurprisingly, the contractor’s legal counsel strongly disagrees. On the contractor’s behalf, he withdraws its tender, after which the client concludes a construction contract with another contractor.
You might think that would be the end of it. But no, that was when the real battle began. The client claimed that the contractor should have continued negotiating. In first-instance proceedings before the Arbitration Board, the client sought an order requiring the contractor to pay it a substantiated sum of almost €1.8 million. The client believed the contractor was not free to stop negotiating. It regarded the contractor’s draft estimate as a price offer, meaning the point of no return had been reached. The contractor’s defence was that sending a draft estimate was an attempt to conclude a construction contract. However, it did not consider it possible to make an acceptable offer at the prices set by the client. For that reason, it withdrew its tender under the clause in question.
The arbitrators first point out that the construction team agreement does not require the contractor to submit a price offer. This remains the case even if the contractor has declared itself willing and able to accept and carry out an assignment. In the arbitrators’ view, sending the draft estimate should instead be seen as notification that no offer can be made, together with an indication of what might be possible. The contractor was not in breach of the agreement by failing to submit a new tender that met the client’s requirements. Moreover, the arbitrators consider that the clause in question does not imply that it serves solely to protect the client. The first-instance arbitrators dismiss the client’s claim.
The client didn’t take no for an answer and appeals. But the appeal arbitrators also find against it. Like the first-instance arbitrators, they conclude that, since the contractor provided the client with a draft estimate by email without being obliged to do so, the point of no return had not been reached. They also find that the disputed clause applies to the contractor, which was therefore entitled to withdraw its tender. As the unsuccessful party, the client must pay the legal costs, as well as the contractor’s legal fees, just as it did at first instance.
Differences in cost estimates, poor communication and unclear contract clauses proved an insurmountable obstacle to the parties building together. Looking for skilled professionals in metal windows and façade elements, and keen to avoid being disappointed? You can work with VMRG members with complete confidence!