Simple building structure, complex façade detailing

The Plus Ultra concept is characterised by high efficiency and, above all, a simple, demountable building structure. The same applies to the new multi-tenant building at Medical Business Park Amsterdam, right next to the AMC. The façade, by contrast, is anything but simple. De Groot & Visser was responsible for the complex façade detailing, including a combination of fire-resistant aluminium unitised façades with external PV fins that also provide passive solar shading and are optimised for each façade orientation.

Commissioned by Kadans Science Partner, Plus Ultra Amsterdam was designed by cepezed and provides laboratory and office space specifically for high-tech companies and organisations in the medical sector. De Groot & Visser is familiar with both the concept and the client. “We have already delivered several similar buildings in the past, acting as the façade partner in the construction team,” says director Anita de Groot. “Kadans has a clear vision when it comes to airtightness, the flexibility of the building’s layout and compartmentation, as well as sustainability and circularity.” 

Fire resistance

Commissioned by Wijnen Bouwgroep, De Groot & Visser fitted the prestigious building with 1,128 m2 of curtain walling and 3,062 m2 of unitised façades. “The aluminium curtain walls are on the ground and first floors and use Hueck’s Trigon 60 system, while the entire high-rise section is built with aluminium unitised façades, also from system supplier Hueck,” explains Anita. “One of the challenges was to achieve fire resistance in the unitised façades. We therefore made every other layer of façade elements around the building fire-resistant. You can’t see this from the outside, of course, because we incorporated it within the units in our workshop.” Although the fire-resistant unit is a standard, tested system from Hueck, it required a number of additional operations in De Groot & Visser’s workshop. “It is more labour-intensive than producing and assembling a non-fire-resistant unit,” Anita says, drawing on her experience. “Airtightness is also always important in buildings of this kind, but it is relatively straightforward to achieve with a unitised façade.”   

PV fins 

All the unitised façade elements were prefabricated, transported to the construction site and prepared for installation of the PV fin structures. “We added extra reinforcement to the units for this. The fins were then attached to the unitised façade in a triangular arrangement. That was quite a challenge too, especially getting the units perfectly aligned. It also required close coordination with the installer and panel supplier, Saint-Gobain Solutions, to get the whole system working.” The PV panels were installed on the fins later, on site, which Anita says was done to minimise the risk of breakage. And it worked. The more than 1,000 m2 of panels have a total capacity of approximately 194,256 Wp. The fins not only generate energy, but also provide passive solar shading, with their design optimised for each façade orientation. This made it possible to use full-storey-high transparent façade sections, bringing in daylight and providing views. This has a positive effect on users’ experience and wellbeing.

BREEAM Outstanding

The extensive efforts of De Groot & Visser and many other VMRG partners helped create an exceptionally sustainable and circular building, which has been awarded BREEAM Outstanding certification. “Kadans is really making its mark with sustainable building concepts that are relatively simple at their core, comprising a steel frame, hollow-core concrete floors and a façade around them,” says Anita. “That is also evident in Plus Ultra Amsterdam. It is a highly effective, circular construction method that offers unprecedented flexibility for the future. The floor plan can be freely configured. All the components can also be easily dismantled or upgraded. The same applies to the unitised façades and curtain walls.” Plus Ultra Amsterdam was completed in September 2023. De Groot & Visser is already working on the next Plus Ultra concept, in Utrecht. To be continued!  

Project details

Plus Ultra, Amsterdam

Client:

Kadans Science Partner

Architect: 

cepezed B.V.

Contractor: 

Wijnen Bouwgroep

Façade contractor:

De Groot & Visser 

System supplier: 

Hueck

PV PANEL SUPPLIER:
Saint-Gobain Solutions 

Glass supplier: 

Scheuten

Other suppliers: 

Comhan, FAAC, Zetsupport, Weerter Paneel Industrie

Question about this story? Ask your question

Who worked on it

Plus Ultra Amsterdam in Amsterdam

  1. Façade contractorDe Groot & Visser
  2. ClientKadans Science Partner
  3. Architectcepezed B.V.
  4. ContractorWijnen Bouwgroep
  5. System supplierHueck
  6. GlasleverancierScheuten
  7. Overige leverancierFAAC
  8. Overige leverancierWeerter Paneel Industrie

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectPlus Ultra Amsterdam
  • SubjectVMRG
  • CompanyDe Groot & Visser
  • CompanyKadans Science Partner
  • Companycepezed B.V.
  • CompanyWijnen Bouwgroep
  • CompanyHueck
Share this article

Advertisement

Follow Gevelbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.