The final reckoning

Mr. Bettina Hertstein www.bouwrechtbedrijf.nl
Mr. Bettina Hertstein www.bouwrechtbedrijf.nl

A school building houses preschool provision, childcare, primary education and youth care. The foundation needs four additional classrooms. After finding a contractor, it quickly concluded a building contract. Just as quickly as the contract was concluded, it was ‘withdrawn’, as the foundation’s director informed the contractor. The contractor was quick to respond.

What happened? The contract stated that construction was to start in the middle of the 1st quarter, so that the classrooms would be ready before the new school year. The foundation had made the UAV 2012 applicable to the works. Less than two months after signing, the contractor received an email from the foundation’s director saying that, due to unforeseen circumstances, construction could not go ahead and that he wished to withdraw the contract. 

It is an understatement to say that the contractor did not take this news well. He informed the foundation that, whether or not the circumstances were unforeseen by the foundation, they remained within its sphere of risk. The foundation was required to honour the contract. The contractor knew his classics. He referred the foundation to paragraph 14 of the UAV 2012, which states that the client is entitled to instruct the contractor to terminate the works in an unfinished state, but that the accounts must then be settled. The contractor is entitled to the contract sum, plus the costs incurred as a result of the works not being completed, less the costs saved as a result of the termination. The contractor could not agree to the contents of the termination letter without payment from the foundation.

The foundation’s director responded again. He said that construction could not go ahead for economic reasons, but that he was still in talks with the municipality. The contractor considered this unrelated to the contract. If the foundation decided to proceed in the autumn, he would still start the construction work. In that case, he would specify the extent to which the delay had increased costs. 

After the contractor’s legal representative informed the foundation of the amount the contractor was claiming as part of the settlement, the foundation’s legal representative told the contractor that the foundation was not bound by the contract because the director had never been granted power of attorney.

In the contractor’s view, that statement meant the foundation had run out of time to play games, so he started proceedings before the Arbitration Board for the Construction Industry. He argued that, in accordance with paragraph 14 of the UAV 2012, the works had been terminated in an unfinished state and the accounts therefore had to be settled accordingly. As he had to complete the works before the new school year, he had already finalised his schedule and staffing for the summer holidays. At the end of May and start of June, he could not immediately deploy his crew on another project. Some of the materials had already been delivered, and the rest could no longer be cancelled without incurring a penalty. His principal claim was for € 140,479.27 excluding VAT, being the difference between the contract sum of € 630,000 and the amount saved, € 489,520.73. The foundation sought dismissal of the contractor’s claim(s).

The arbitrators delivered the lesson. Their painstaking scrutiny established that there had been a change in the foundation’s board, with the current board taking a different view of the new classrooms and withdrawing the permit application for that reason. The board had wanted to discuss an alternative with the municipality, but that plan fell through. This is entirely consistent with the earlier communication to the contractor about withdrawing the contract, which made no mention whatsoever of any possible lack of authority on the part of the signatory acting for the board at the time. 

The foundation did not dispute that the intention was to have the classrooms ready before the new school year. The foundation’s claim that the contractor should have waited until the environmental permit had been granted is not supported by the UAV 2012 (paragraph 5, subsection 1(a)). Obtaining the necessary permits in good time was the foundation’s responsibility. Furthermore, the foundation itself had withdrawn the permit application.

The arbitrators also rejected the foundation’s objections to the various items in the claim. The claimed overheads, profit and risk were also awarded, as the foundation had raised no specific defence against them. The foundation’s final balance was in the red. The contractor could not have been more satisfied with the award.

And, as a colleague used to say to contractors: “There’s no better job than one you don’t have to build!” Have plans that can go ahead? Then count on the expertise of VMRG members!  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectVMRG
Share this article

Advertisement

Follow Gevelbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.