A substantial housing development has been created on a complex, noisy site in Amsterdam Bos en Lommer, directly beside the A10. It was a challenging project from the outset, but one that has succeeded thanks to a unique collaboration between the designers, builder, investor, local authority and residents, as we can now safely conclude. Rhapsody combines high-density construction with generous green space and water, and has already won numerous awards.
Rhapsody was built on Jan van Schaffelaarplantsoen, on the edge of the Kolenkitbuurt. For a long time, the vacant site served as a green space and meeting place for the neighbourhood. In late 2014, the municipality of Amsterdam invited tenders for the site. The winning design by Tangram Architectuur, commissioned by the SBB (Smits Bouwbedrijf)-De Nijs JVS construction consortium, is characterised by its soft, rounded forms. According to the architect, these play an important role in making the high density more acceptable and contribute to the compactness of the blocks. “They also deflect noise from the A10 ring road significantly. We avoided using a gallery-access design, which sets the scheme apart from the usual solutions for noisy sites, such as noise barriers.”
Predictable construction
At the construction consortium’s suggestion, Alkondor joined the project team to develop the optimum solution for the façades. “We faced a number of challenges here, including working together with the other parties involved,” says Jan Bergman of Alkondor. “In the project team, we aligned the design with the technical possibilities, while staying as close as possible to the architectural and financial brief. This helps prevent surprises on site. All the partners therefore invested a great deal of time and energy in the engineering, so we could build in a ‘predictable’ way.” Speaking of collaboration, Rhapsody is a unique top-down, bottom-up project. This means that contact with the neighbourhood was established at an early stage. This collaboration brought about a successful blend of ideas. For example, the courtyard, with its garden and ponds, is freely accessible, and a new meeting place, the KolenkitKas, has been created. Activities are held there, and there is even a guest house for visiting family members.
Harbour windows
Rhapsody comprises five buildings with a total of 250 homes, 590 m2 of commercial space at ground-floor level and 212 parking spaces in underground car parks. Alkondor mainly used Kawneer RT 72 aluminium window frames on the project. “Depending on their position, the frames were also specified with fire-resistant or sound-insulating performance,” says Bergman. Tangram Architectuur deliberately avoided a gallery-access concept for Rhapsody. “To give residents facing the ring road (where there are noise requirements) the option of purge ventilation, we used ‘harbour windows’ for these frames. We also worked closely with VPT Versteeg, the façade cladding supplier, to ensure continuity in the vertical articulation of the façade and provide the right connection details. The frames feature decorative box sections that align with the façade cladding.” Hans den Hollander of Kawneer adds: “That is the advantage of our modular system: it is perfectly possible to vary the inner or outer face without compromising thermal insulation.”
Modular construction
Bergman says that the modular construction of the window frames was a key reason for Alkondor choosing Kawneer. “The modular profile system enables us to manufacture frames efficiently in our factory. The product is ideally suited to projects such as Rhapsody, which have additional requirements. The highly insulated RT 72 profile series, combined with triple glazing, delivers excellent performance.” Den Hollander adds: “The units installed at Rhapsody underwent extensive wind and watertightness testing at our test and training centre in Harderwijk. As you would expect, they meet the specified requirements.” It is therefore hardly surprising that Rhapsody has such outstanding energy performance. The building even has a negative EPC of minus 0.037, an improvement of 109% on the statutory requirement at the time of submission. The entire complex is one large energy factory: after deducting their own consumption, residents feed energy into the grid. This is made possible in part by the solar cells on all the roofs.
The housing project has a highly flexible design. The blocks can continue to be arranged in different configurations, with homes ranging from 50 to 120 m2 and larger, both now and in the future. This takes account of the needs of current and future residents and ensures the development remains valuable for many years. Bergman says: “The key here was to get the right people around the table at an early stage, so we could build well and predictably. Additional requirements, such as sound insulation and fire resistance, have been integrated effectively, resulting in a high-quality product that provides the level of comfort residents can expect in a complex like this.” Den Hollander calls it a wonderful development. “Rhapsody has won numerous awards, and deservedly so.”