A construction contract in several instalments

Mr. Bettina Hertstein www.bouwrechtbedrijf.nl
Mr. Bettina Hertstein www.bouwrechtbedrijf.nl

Some legal disputes leave people asking afterwards: ‘How could this have happened?’ It is standard practice for the parties to agree on matters such as the client’s requirements for the building work, the associated costs and the terms and conditions. If agreements are not recorded clearly enough, things can go badly wrong for the parties if a problem arises, because of the consequences under the rules of evidence. To the frustration of both, the client and his contractor found this out through bitter experience, too late.

What happened? The client bought an old house that he wanted to have renovated. To this end, he contacted the contractor. Once they had reached a verbal agreement, the contractor began work. He sent the client a total of six (interim) invoices for his work, one third of which remained unpaid. The relationship deteriorated to such an extent after the client asked the contractor for a quotation for the remaining work that the client terminated the contract. The contractor then sued the client in court, seeking payment of the outstanding balance of his invoices. The client denied that he still owed the contractor any money. He also filed a counterclaim based on an agreed lump sum or target price.

The question is what agreement did the parties actually enter into, and what kind of agreement did the client therefore terminate? Since nothing at all was put in writing or recorded digitally, however briefly, and the parties disagreed about the scope of the renovation and its cost, the court ordered the client to prove that a fixed price or target price had been agreed. According to the client, a fixed price of € 70,000, including VAT, had been agreed for the work. The contractor said he could not quote a fixed amount or target price because he was not responsible for the entire project. The client would carry out some parts of the work himself, with family and others. Moreover, the contractor always worked on a time-and-materials basis on projects involving old buildings, and this house was no exception. The agreed hourly rate was € 32.50, excluding VAT.

In its decision, the court took into account that the contractor was a professional and the client a relative layman. It was not necessarily the case that the contractor had not intended to enter into a time-and-materials agreement, but it was incumbent on him to ensure that the costs were not open to multiple interpretations by either party. After hearing witnesses, the court ruled that the client had succeeded in proving that the agreement included a target price of € 70,000.

The contractor then appealed to the Court of Appeal. He sought to have the District Court’s judgment set aside and his original claim upheld. The Court of Appeal also considered whether the parties had agreed a time-and-materials contract, as the contractor claimed, or a fixed-price or target-price contract, as the client maintained. In the absence of sufficiently specific facts and circumstances, the Court of Appeal could not establish whether a time-and-materials contract had been concluded. Unlike the District Court, it also found that it had not been established that the parties had agreed a fixed price, or a target price of € 70,000 including VAT. The client’s statements were inconsistent. By contrast, the contractor’s ‘timesheets’ were no more than a filled-in ‘template’ from which no conclusions could be drawn. The Court of Appeal therefore found that the client had not succeeded in proving that a fixed price or target price had been agreed. Since the Court of Appeal was also unable to establish that the parties had entered into a time-and-materials contract, it followed that the price payable by the client to the contractor had to be a reasonable one. Article 7:752(1) of the Dutch Civil Code provides: If the price has not been determined when the contract is concluded, or only a target price has been determined, the client is liable to pay a reasonable price. In determining the price, account is taken of the prices normally charged by the contractor at the time the contract is concluded, and of the expectations he has created regarding the likely price. The Court of Appeal will give the parties an opportunity to explain their positions in further detail, by way of written submissions, on what they consider a reasonable price for the work carried out by the contractor. The final decision will therefore only come after both parties have filed their submissions. Reaching an agreement between themselves remains an option.

Straight to the main event, without the hassle? With the VMRG Quality Requirements and Recommendations, you’re guaranteed a ringside seat! For clear agreements with façade construction professionals, visit www.vmrg.nl.

‎‎

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectVMRG
Share this article

Advertisement

Follow Gevelbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.