Amsterdam UMC entrance pavilion: Packed with challenging details

The new entrance building at Amsterdam University Medical Centre has been designed as a glass pavilion. Its soft, rounded forms leave almost no straight lines to be seen. The pavilion is therefore in stark contrast to the existing, no-nonsense buildings dating from the 1980s. Façade contractor Vorsselmans was tasked with delivering the building envelope for the new entrance building, which is packed with challenging details. We spoke to project manager Luc Kuipers.

The entrance area at Amsterdam UMC has been transformed from a jungle of asphalt and cars into a green space for patients, visitors, staff, students and local residents. The new main entrance makes a refreshing impression with its rounded forms and curved glass, set amid the newly landscaped park. “The pavilion has two levels, with the main entrance to the hospital on the first floor,” Kuipers explains. “There is, of course, also access to the pavilion from ground level (the parking level), after which visitors are guided up to the main pavilion level via the escalator or stairs, through a circular atrium.”

3D engineering
Vorsselmans has been involved in this challenging new-build project from the very outset. “Following positive experiences on an earlier project at UMC Utrecht, contractor MedicomZes asked us to contribute ideas for the building envelope of the glass pavilion here in Amsterdam,” says Kuipers. “It was a project with a great many curtain walls, most of them in curved forms, both concave and convex, apart from the walkways. Looking at the floor plan, you see only circles of various radii. To make the design buildable and engineer the complex junctions in great detail, we modelled everything in 3D.” Although the entrances on both floors are identical in size and design, each with a revolving door and two sliding doors, their junctions differ considerably because the curtain walls on the two floors have different shapes. “The architect had already given careful thought to the undulating shapes of the curtain walls, concave and convex, to make the overall geometry work as one smooth, continuous movement. We were able to adopt that shape.”

The cap
Another interesting detail is the pavilion roof, which the architect calls ‘the cap’, Kuipers continues. “The roof is oval and higher in the middle than at the ends. Project the undulating curtain wall beneath it and it quickly becomes clear that this creates some interesting details. The architect initially proposed having the curtain wall follow the shape of the roof, but that proved virtually impossible, or at least well over budget. The transoms would have had to be made at all sorts of angles, as would the glass, which would also have needed to be curved, either concave or convex. We proposed an alternative with a flat top edge at varying heights, concealed behind the ceiling. The ceiling finish of timber slats still creates the intended effect.” Vorsselmans delivered the entire façade using Schüco’s FWS 60 series, with vertical structural glazing and no pressure plates or cover caps. The transoms were curved by Kersten Europe, while the curved panels for areas including the walkway roof edges and the fascias of the draught lobbies were manufactured by VPT Perforeertechniek.
Challenging details
The entire pavilion is characterised by challenging details. Kuipers highlights a few: “At the top junction of the walkways, the available height for our curtain wall was very limited. There was virtually no adjustment tolerance. We used a trick here, fitting a narrower transom from the Schüco FWS 50 system in this location. This gave us a little more adjustment tolerance. By positioning the pressure plate and cover cap eccentrically rather than centrally, and aligning them at the bottom, the difference is not visible. Another unique detail is the curtain wall’s connection to the steel structure at the top of the pavilion. It is a tangle of steel beams and bracing that was not even included in the model at first. We encountered steel in all kinds of directions. It was our job to make the junctions with our curtain wall airtight and insulated. We used various types of anchor for this.”
According to Kuipers, installing the façades was also quite a job. “We used various pieces of equipment, including a telehandler, a boom lift and a special flexible glass vacuum lifter that could be set to the correct curve, concave or convex. We completed the project in April, finishing the internal junction with the existing building down to the last detail. Allpro supplied all the folded metalwork for this. All in all, installation went perfectly. The result is truly fantastic.”
A business enquiry for Architect at Work? Get in touch
Wie aan Entreepaviljoen werkte
- façade contractorVorsselmans NVIn this story
- clientMedicomZesIn this story
- contractorBouwcombinatie MedicomZes/HOMIJ Technische Installaties/Van Kessel Sport en CultuurtechniekIn this story
- architectOntwerpcombinatie Nuy Van Noort/ temp.architecture.urbanism/Studio BLADIn this story
- System supplierSchüco NederlandIn this story
- internal claddingAllpro BVIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectEntrance pavilion
- SubjectVMRG
- CompanyVorsselmans NV
- CompanyMedicomZes
- CompanyBouwcombinatie MedicomZes/HOMIJ Technische Installaties/Van Kessel Sport en Cultuurtechniek
- CompanyOntwerpcombinatie Nuy Van Noort/ temp.architecture.urbanism/Studio BLAD
- CompanySchüco Nederland