Congestion is no fun. Congestion in, for example, the nose, traffic or a data or electricity network is always a nuisance. In effect, we are talking about a blockage. Not the kind of blockage that can be cleared by playing peekaboo. A client and a contractor discovered that there was no ‘magic spell’ available to resolve the congestion they were suffering from.

What happened? The client and contractor entered into a construction contract for the construction of a shell commercial unit. Work began on 7 June 2023. It was agreed that the works would be completed and ready for use, including an electricity connection, within 200 working days from the start of construction. According to the client, completion took place far too late. The question of whether it was late, by how long, and who should be held responsible led to mutual accusations that brought no solution. If there had been any delay, the contractor argued, it should be treated as a case of force majeure. In short, he blamed his electrician and grid congestion for everything. The dispute had by then grown to such proportions that only an appeal to the wise arbitrator could set the ‘everything flows’ of the philosopher Heraclitus in motion.

According to the client, the commercial unit should have been completed by 18 April 2024 at the latest, but the contractor did not complete it until 27 November 2024. The client considers this 141 working days late. He claims payment of 141 days multiplied by the daily penalty of € 60, amounting to € 8,460, plus statutory interest up to the date on which he filed his claim with the Council of Arbitration for Construction Disputes on 24 February 2025. The contractor takes a completely different view. He maintains that the construction period ended on 5 July 2024 and that he completed the works well within the construction period. He disputes the client’s claim and considers that no delay is attributable to him. After all, construction of the commercial unit was already complete in September 2023. This was without the paving, however, as he could only lay it once the service connection was complete. He had applied for the electricity connection on 30 March 2023, for the earliest available slot, namely the week of 2 October 2023. The fact that the electricity connection was not installed until the week of 7 October 2024, due to errors by the electrician and the absence of the necessary permits, was not his responsibility. He repeatedly urged the electrician to complete the work on time. Since he was entirely dependent on the electrician, he considers this a case of force majeure.

The arbitrator considers that the electrician’s errors do not constitute force majeure for the electrician, and therefore neither do they for the contractor. It was only at the hearing that the contractor raised the point that the electricity grid had insufficient capacity to connect the commercial unit. He therefore had to wait until the week of 7 October 2024, when new cables and a new transformer station had been installed. For this reason too, the contractor argued, the delay should not be at his risk or expense. The arbitrator considers that, quite apart from the fact that this defence was raised too late, as the client also submits, it cannot help the contractor. Moreover, grid congestion has been present in the area where the commercial unit is located since 2018. It was therefore foreseeable to the contractor when he entered into the construction contract that a delay could occur. On the basis of the parties’ respective submissions concerning the completion date and the number of demonstrably non-working days, the arbitrator finds that the construction period was exceeded by 141 working days. In the arbitrator’s view, the commercial unit should have been ready for use on 18 April 2024. The contractor’s application to reduce the penalty is unsuccessful, as a reduction is possible only if fairness evidently requires it. That could be the case if applying the penalty clause in the circumstances produces an excessive and unacceptable result. In the arbitrator’s view, that did not happen here, and there is no reason to reduce the penalty. The arbitrator orders the contractor to pay the amount claimed to the client, plus the statutory interest claimed.

Neither party felt a sense of elation after this ruling. But for the contractor too, as the unsuccessful party, everything flows. Would you like to build on something that is always changing yet remains the same? Then choose the services offered by VMRG members. You won’t have to play peekaboo with them. 

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectVMRG
Share this article

Advertisement

Follow Gevelbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.