Masterpiece by Mr Bettina Hertstein | Little mishaps

That construction and renovation work does not always go smoothly is regarded by cynics as common knowledge. Fortunately, most projects run to everyone’s satisfaction, but an angry party may sometimes make a rash move. A bad landing can then prove painful and costly, as became clear later in A&E.
The parties entered into a building contract for the conversion and renovation of three shell homes in a listed building. They later recorded further agreements, including one concerning the completion date. An overview of invoices, entitled “handover report”, did not go down well with the client. He disputed that the work had been completed. Not long afterwards, the architect wrote: “On behalf of the client, I hereby require you not to appear at or near the work in X again (…). Trust has been withdrawn and the contract terminated.” The contractor replied that although there was a difference of opinion over the quality of the façade render and paintwork, his painter had already agreed to rectify some ‘little mishaps’. The contractor pointed out that, now the client was demanding a buy-out on quality grounds, it first needed to be established whether there were any defects and, if so, what the cost of putting them right would be. He would forward a report he had commissioned on the matter as soon as he received it, so that “we can arrange a meeting immediately afterwards”. A year after the originally agreed completion date, the client wrote: “we have been trying for a long time to arrange the final handover of project X”. The client refused to pay the contractor’s invoices. Eventually, the contractor had a lien placed against the client’s assets. Since then, further discussion and the carrying out of the remedial work offered by the contractor have proved impossible. The arbiters (of the Arbitration Board for the Construction Industry) are asked to administer first aid.
The client seeks to set off the amounts on the invoices against his claim for the cost of remedial work and for the loss he says he suffered because handover did not take place. Having reconstructed events from the circumstances described by the parties, the arbiters find that the work must be regarded as having been handed over on or around the agreed completion date. The fact that this was also clear to the client is evidenced, among other things, by the WhatsApp messages they exchanged. It was only after receiving the email with the invoice overview and the attachment entitled “handover report” that the architect replied that, in his view, no notification of completion had been given and the work still had defects. It was certainly unwise of the contractor to give the email attachment that title, but the architect’s reply shows that the alleged defects mainly concerned the rendering and painting, and were so minor that they did not prevent handover. The contractor’s clumsy manoeuvre does not mean that the work had to be considered incomplete. As for termination of the contract, the client provided no evidence that he had formally demanded performance from the contractor, let alone that he had served a notice of default allowing a reasonable period for performance, as required by law. Nor had any notice of liability been given. In addition, the arbiters found that the contractor had offered to put right the few points, the ‘little mishaps’, in the paintwork in accordance with the report by Verf Advies Centrum. The arbiters also inspected the paintwork on site themselves and agree with the finding that it generally meets the required standards. As for the render on the restored façades of the listed building, an inspection by Afbouw Gevelsupport found that it met the applicable standards. The arbiters endorse that conclusion too.
By prohibiting the contractor from returning to the site, the client made it impossible for the contractor to fulfil his remedial obligations. It was the client, not the contractor, who was in default. The client did not validly terminate the contract. The arbiters therefore reject the client’s claims for set-off in respect of remedial costs and other alleged losses. It is clear who made the big mistake and must therefore pay the invoices, interest and all further costs incurred in the proceedings.
Want to avoid a costly mistake? Trust each other, but make sure to document important milestones properly. And to keep up with the latest developments in metal windows and façade elements, visit www.vmrg.nl!