The value of something or someone and the appreciation they receive often fail to align. Usually, this is because emotion gets in the way of objective assessment. Love is blind, but once the romantic agreement has been made, a commitment such as marriage is simply a business agreement. Once the contract has been signed, it is all about proper execution. And sometimes that is where things go wrong. The construction industry is no different, as clients discovered when the extension to their home was never completed.

The start of the building work was not romantic, but the clients had complete confidence in their contractor. He was to renovate the ground floor of their home and their garage, and install a prefabricated extension. After pouring the foundations and the concrete floor, the contractor began installing the extension. A few months after work began, the clients complained about various defects in the work carried out. They commissioned experts to investigate. They identified numerous defects, including in the rear façade portal, the floor joists, the concrete floor, the screed and the load-bearing walls. The clients gave the contractor one month to complete the work. The contractor informed them that, rather than completing the work, he would prefer to pay them compensation. The clients replied that they could not determine the likely cost of repairs. They also confirmed that the contractor had told them that same day that he was stopping work. They informed the contractor that he was therefore in default and that they would start proceedings. The contractor immediately replied that he would seek legal advice. Both sides then remained silent for a few weeks. The clients subsequently emailed the contractor to say that they were converting their claim for completion of the work into substitute damages. Some time later, the clients obtained a prejudgment attachment of assets held by third parties. An urgent site inspection by the Council of Arbitration in Construction Disputes also took place. That was not the end of the story, however, as the parties met before the Council to settle their dispute.

Before the Council, the clients sought, among other things, to have the agreement between the parties terminated on the grounds of the contractor’s breach of contract. They claimed repayment of the full amount paid to the contractor, as well as payment of the demolition costs and the additional costs of rebuilding the extension. The contractor disputed the clients’ claims but acknowledged that he had made mistakes. He argued that there was no need to demolish what he had already built, as it could still be repaired. The arbitrators found that the contractor had wrongfully abandoned the work and that, as shown in the expert reports whose findings the contractor had not substantively challenged, it contained several serious structural defects. The arbitrators considered termination justified and granted the request to terminate the agreement. In this situation, termination means that the contractor must repay what the clients have already paid, less the value they received from the work carried out by the contractor. The arbitrators followed the expert advice, which explained why demolishing the entire structure and rebuilding it was the only option, but found that some of the contractor’s work would retain its value after demolition. This included “the architect’s and draughtsperson’s work, structural engineering, EPC calculation, propping and demolition work, piling, earthworks and sewerage”. In addition, “various materials, such as window frames, steel, timber structures, rooflights and the roof covering (including its insulation), can be reused in whole or in part”. The arbitrators estimated the value of the work carried out and the materials to be reused at €60,000. The clients had paid just under €110,000. The contractor must repay the difference to the clients. The contractor must also pay the clients the reasonable costs of demolition and the additional costs of rebuilding. 

Moving from hope to demolition was not what the clients had expected when they said “I do” to the contractor. They have no choice but to dry their eyes and start again. One positive is that they can reuse some of the materials. You can read about the value of circular construction and how VMRG and its partners approach reuse at www.circulairegeveleconomie.nl.  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectVMRG
Share this article

Follow Gevelbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.