U-turn over Uw-value

However smoothly the construction and handover may have gone, once the client is settled in an armchair, reminiscing about the first party in their new home, they may still start to wonder whether they really got everything they believe they were entitled to. A dispute could still arise over the difference between expectations and what the parties had actually agreed.
In the client’s view, they had also invested a great deal of energy in the new home built by the contractor, which was intended to deliver maximum energy savings. After handover, a discussion arose about, among other things, the absence of solar shading and the number of plus signs agreed for the high-performance glazing installed by the contractor. An expert report commissioned by the client did not help the parties understand each other’s positions.
Fortunately, the arbitrator had enough energy to examine not only the parties’ positions and the conclusions in the expert report, but also to visit the property in person.
It is undisputed that HR++ glazing was installed, as specified in the specifications and technical description. However, the environmental permit is also part of the contract documents. The Building Decree report forms part of that permit. The report states that, although a U-value of 0.7 is specified in the technical description, triple glazing (HR+++ glass) would probably be needed to achieve that value. The expert from the building consultancy calculated the Uw-value of the combined (wooden meranti) frame and glass in the home as 1.0. According to that expert, the glazing should have been HR+++ to achieve a glass U-value of 0.7, and thus the required EPC. The client’s position is that this is what the contractor should have done. The contractor disagrees, believing that triple glazing provides a higher level of insulation than required. In their view, an alternative would be to apply film to the double glazing.
The arbitrator agrees with the client’s position and the conclusions of the expert report. Referring solely to the technical description as a contract document is insufficient. As the contractor stated at the hearing, they were not aware of the environmental permit. Since the environmental permit is also part of the agreement, the contractor is deemed to have been aware of it. The arbitrator considers the contractor’s proposed alternative of applying film to the double glazing to be a matter of the past. The arbitrator therefore awards the client the costs claimed for rectification.
The client also argues that, although the parties did not agree to solar shading, it should be installed at the contractor’s expense because solar shading was included in the EPC calculation. The arbitrator does not agree. The fact that solar shading was included in the EPC calculation does not mean that its supply was agreed as part of the contractor’s work. Solar shading is not mentioned anywhere in the contract documents, as the expert also noted. The arbitrator further points out that solar shading is usually installed as a movable item by the occupant, at their own expense, after handover, as the client has done. This claim is dismissed.
Despite everyone’s best efforts, things do not always go as expected. Sometimes a technical and legal U-turn is needed to get back on the right track.
Looking for a high-performance façade consultancy without detours? Companies bearing the VMRG Keurmerk deliver guaranteed quality in façades!
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- SubjectVMRG