Uniform Administrative Conditions for Integrated Contracts (UAV-GC 2025)

Uniform Administrative Conditions for Integrated Contracts (UAV-GC 2025)

A full title is needed for the name of this revised ‘comprehensive set’ of general terms and conditions for the construction industry, commonly known as UAV-GC. The conditions go hand in hand with the (also) revised MBO, the Model Basis Agreement. The new version (previous versions date from 2000 and 2005) was launched on 14 January 2025. After a general introduction to these conditions, I will first discuss several legal points of interest for façade contractors. I will then outline the changes in the 2025 version and take a closer look at some points relevant to façade contractors.

The UAV-GC are used for an integrated contract, with design and construction under one roof. The Client contracts with the Contractor, who is responsible for both design and construction, depending on the Client’s choice of a ‘more or less integrated’ arrangement. The Parties set out their choices in the MBO (and Annexes). The Client always prepares the (functional) Requirements Specification. The commission to the Contractor reflects the Client’s choice as to whether the Requirements Specification is to be developed further from the Schedule of Requirements, Preliminary Design or Final Design. As a fourth option, the Client may commission elements of the work at different levels of development. There is no contract administration. 

Bilateral agreement

Under the UAV-GC, a façade contractor engaged by the Contractor is referred to as an Independent Assistant. The UAV-GC and MBO are agreed between the Parties (with a capital letter). These are the Client and the Contractor. A bilateral agreement between the façade contractor and the UAV-GC Contractor (as the façade contractor’s client) is therefore of the utmost importance. This is all the more important because, before entering into a contract as an Independent Assistant, the façade contractor may be involved in a construction team. Since 2020, three new model construction team agreements have been launched. Under these, the construction team phase may be followed not only by a construction phase under the UAV 2012 (2025 version), but instead by one under an MBO with UAV-GC. The construction team agreement is entered into between the client and the contractor. As a member of the construction team, the façade contractor must also ensure that it always enters into a bilateral agreement with the (construction team) contractor for its design input, regardless of whether the construction team phase is followed by a construction phase under the UAV or UAV-GC.  

Changes

Changes in the UAV-GC 2025 (paragraphs) and MBO (articles) compared with the UAV-GC 2005 and MBO

  1. Parties’ obligation to act proactively and interact (§ 2a UAV-GC 2025)
  2. Changes instructed by the Client (§ 14 UAV-GC 2025)
  3. Changes initiated by the Contractor (§ 15 UAV-GC 2025)
  4. Liability before and after completion (§ 28a and § 28b UAV-GC 2025)
  5. Intellectual property and the Contractor’s Inventions (§ 40 and § 40a UAV-GC 2025)
  6. Dispute resolution (§ 47 UAV-GC 2025)
  7. Recording design work by component (article 5 MBO)
  8. Implementation of the Quality Assurance in Building Act (Wkb) (article 13 MBO)
  9. Information from the Client (article 7 MBO and § 3 UAV-GC 2025)
  10. Formation of the Agreement (article 19 MBO)

The UAV-GC 2025, together with the MBO, Annexes and Explanatory Notes, is a 272-page ‘booklet’. I will focus on two important changes (points 1 and 5 above).

Campfire clause

Section 2a of the UAV-GC requires the Parties to act proactively and interact. The Parties (with a capital letter, meaning the Client and Contractor), not all parties. The provision is known as the ‘campfire clause’ and is intended to encourage ‘desirable behaviour’ through lots of consultation, and more consultation, with ongoing dialogue! A façade contractor may participate as an Independent Assistant in a project carried out under the UAV-GC, but must enter into a separate contract with its client (usually the Contractor under the UAV-GC). How proactive and interactive does the façade contractor need to be? And will the UAV-GC Contractor also behave in accordance with Section 2a towards its Independent Assistant, the façade contractor? The UAV-GC and MBO do not exactly have a reputation for promoting good contractual relationships, but, in my view, they are now slowly moving in the right direction. Section 2a is a guiding principle, but it is not legally enforceable. Nevertheless, a Party that fails to show even basic decency during the collaboration can be held to account for that. I consider this section useful, but particularly because I expect it to lead to better conduct and attitudes throughout the construction supply chain. If it works in construction, perhaps we should also send our political leaders to a campfire meeting!

Intellectual property

Chapter 15, ‘Intellectual Property Rights’, has been expanded with two sections specifically concerning patents, Sections 40a and 40b. A new paragraph 9 has also been added to Section 40, requiring the Contractor to pass on the provisions of Chapter 15 in its entirety, that is, Sections 40, 40a and 40b, to the assistants it engages. This means that the Contractor must obtain a licence from an assistant (for example, the façade contractor) whose patent forms part of the basis for the Contractor’s Tender. Façade contractors, take the initiative, and do not forget the financial aspects when discussing your own patent. Also pay attention to Section 40b, which concerns ‘inventions eligible for patent protection’ made during performance of the Agreement. All in all, the new UAV-GC seems to offer façade contractors more opportunities!  

Mr Bettina Hertstein 
www.bouwrechtbedrijf.nl

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectVMRG
Share this article

Follow Gevelbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.