VMRG says price adjustments in the façade sector are unavoidable

Hans Zwaanenburg, director of VMRG
Hans Zwaanenburg, director of VMRG

The façade construction sector is increasingly concerned about rising costs and longer lead times, with serious consequences for cash flow and growing fears of insolvencies. This is all due to the unexpected sharp increase in the costs of building materials, including aluminium and steel, and longer lead times. These materials account for a significant proportion of the cost of façade applications, such as curtain walls and unitised façades. 

The trade association for metal façade construction, VMRG, reports that companies have faced successive double-digit price increases over the past year, as well as having to make additional investments from their own capital to weather the crisis. Hans Zwaanenburg, director of VMRG, says: “These developments mean that façade contractors have less and less financial headroom to absorb the impact themselves. Price increases for upcoming projects are unavoidable, and so too, above all, are price adjustments to projects already under way.” 

Explosive price increases for aluminium and steel 

Steel prices have risen explosively in recent months and have now more than doubled compared with mid-2020. Aluminium is no different, with prices now at their highest level in 10 years. “This is a serious problem for façade construction,” says Zwaanenburg, “particularly for projects that have already been approved and are under way, with longer lead times and insufficient allowance for these explosive price increases. In 2020, aluminium or steel accounted for around 25% of the cost of a façade. That figure has now almost doubled, and the end may not yet be in sight.” 

Putting the interests of the project first

The small consolation is that the façade construction sector is not alone in this. The entire raw materials market is currently unstable, facing upward price pressure and longer lead times. These are partly due to supply chain problems in the production process, which have their roots in the pandemic. The aluminium and steel markets have been affected more than most. Zwaanenburg stresses the importance of putting the interests of both new and ongoing projects first, and keeping the conversation going. “The terms and conditions agreed between contractor and façade contractor can certainly help. This is particularly true when there is also an understanding of what is reasonable and fair, and therefore of the shared interests of the project.”

Viable solutions

The market is becoming increasingly transparent, bringing parties in the construction process and end users closer together. The operating costs of a building are becoming increasingly important to end users, making the lowest price less decisive. The trend is towards choosing the most economically viable and sustainable solution, and this will become increasingly common in future. “A sustainable, low-maintenance product delivers considerably greater cost savings during the operational phase than any savings achieved by making concessions simply to secure a lower purchase price,” says Zwaanenburg.

A different approach

Innovation and forward-looking developments require additional investment from the façade sector. Simply supplying a product is no longer enough. “The industry is increasingly expected to contribute its expertise during the design phase and help develop more efficient, sustainable solutions. The façade sector is becoming more of a partner in the process, and this way of doing business calls for a different approach,” says Zwaanenburg. “Manufacturers and suppliers are becoming supply chain partners, contributing their knowledge and experience from the design phase rather than simply supplying a product. This requires not only ‘innovation and financial’ efforts to deliver the low-maintenance, adaptable façades being requested, but above all close collaboration between the parties. The shared interests of the project must come first, while each party is also adequately rewarded for its contribution. Ignoring this undermines the continuity of businesses, not only in façade construction but also among contractors. It is therefore important to keep the conversation going.” According to Zwaanenburg, this includes discussing necessary adjustments to prices or delivery times during a project.  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeCollaboration in the facade industry
  • SubjectVMRG
Share this article

Advertisement

Follow Gevelbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.