VMRG sees price adjustments in the façade sector as unavoidable

The façade construction sector is increasingly concerned about rising costs and lead times, with serious consequences for cash flow and fears of insolvencies. This is all due to the unexpectedly sharp rise in costs and longer lead times for construction materials, including aluminium and steel. These materials account for a significant share of the cost of façade applications such as curtain walling and unitised façades.
The trade association for metal façade construction, VMRG, reports that companies have faced rapidly successive double-digit price rises over the past year, as well as having to make additional investments from their own funds to weather the crisis. Hans Zwaanenburg, director of VMRG, says: “These developments mean that façade contractors have increasingly little financial headroom to absorb the impact themselves. Price increases for upcoming projects are unavoidable, but even more so are price adjustments to projects already under way.”
Explosive price rises in aluminium and steel
Steel prices have risen explosively in recent months and have now more than doubled compared with mid-2020. The same is true of aluminium, whose price has now reached its highest level in 10 years. “This is a serious problem for façade construction,” says Zwaanenburg, “particularly for projects that have already been approved and are under way, with longer lead times and insufficient allowance for these explosive price rises. In 2020, aluminium or steel accounted for about 25% of the cost of a façade. That share has now almost doubled, and the end may not yet be in sight.”
Putting the interests of the project first
The small consolation is that façade construction is not alone in this. The entire commodities market is currently unstable, facing upward price pressure and longer lead times. These are partly due to supply problems in the production chain, which stem from the pandemic. The aluminium and steel markets have been affected more than most. Zwaanenburg stresses the importance of putting the interests of both new and ongoing projects first, and of keeping the dialogue open. “The terms and conditions agreed between the contractor and façade builder can certainly help. This is especially true when they are also guided by reasonableness and fairness, and therefore by the shared interests of the project.”
Cost-effective solutions
The market is becoming increasingly transparent, bringing parties in the construction process and end users closer together. The operating costs of a building are becoming increasingly decisive for end users, making the lowest price less influential. The trend is towards choosing the most economically viable and sustainable solution, and this will become increasingly common in the future. “A sustainable, low-maintenance product delivers significantly greater cost savings during the operational phase than any savings achieved by making concessions simply to stick to a lower purchase price,” says Zwaanenburg.
A different approach
Innovation and forward-looking developments require additional investment from the façade sector. Simply supplying a product is no longer enough. “The industry is increasingly expected to contribute its expertise during the design phase and help develop more efficient, sustainable solutions. This means the façade sector is becoming more of a partner in the process, and this way of doing business calls for a different approach,” says Zwaanenburg. “Manufacturers and suppliers are becoming chain partners, contributing their knowledge and experience from the design phase rather than simply supplying a product. This requires not only ‘innovative and financial’ efforts to deliver the low-maintenance, adaptable façades being sought, but above all close collaboration between parties. The shared interests of the project must come first, and parties must also receive fair compensation for their work. Ignoring this undermines the continuity of businesses, not only in façade construction but also among contractors. That makes it important to keep the dialogue open.” According to Zwaanenburg, this includes discussing necessary interim adjustments to prices or delivery times.