For the construction of a luxury home, a contractor engaged a supplier of a well-known brand of stone wool for a thermal façade insulation system. They had been doing business together for years, and everything had always gone well. Until, one time, it did not. That is when it helps to have not only technical expertise, but also some understanding of the legal ‘rules of the game’.

In early March 2016, the supplier delivered the ordered materials to the contractor. The thermal façade insulation system R was intended for the exterior walls of the home, which were to be finished with white render. Product R was new to the Netherlands, but had already been in use in other countries for some time. Later that year, the contractor handed the home over to his client. The occupant enjoyed his new home to the full for two years, but in August 2018 he reported cracks in the external façades to the contractor. After waiting for a while to see how the cracking developed, the contractor established in mid-October 2018 that the situation had worsened. In November 2019, he engaged a third party to measure the moisture content in the external façades. By then, façade insulation system R was no longer part of the manufacturer’s range. After commissioning Technisch Bureau Afbouw (TBA) to investigate the cracking and moisture problems, the contractor received its report dated 16 January 2020, which concluded that the base coat and mesh layer in the R façade system absorbed moisture very quickly, causing hygrothermal stresses in the façade insulation system. 

On 30 January 2020, the occupant held the contractor liable for the damage he had suffered. After the contractor sent the TBA report to his supplier on 9 February 2020, the supplier involved the manufacturer to investigate the cause of the damage further. On 26 February 2020, test drillings were carried out at the home in the presence of all parties. On 16 April 2020, the manufacturer wrote to the supplier that it had concluded that the contractor had made various errors when installing the façade system. The contractor proposed that the three parties, himself, the supplier and the manufacturer, share the repair costs. The supplier rejected that proposal, as well as the contractor’s subsequent attempt to reach a joint solution. The contractor then proceeded to repair the external façades himself. The cracks in the façades were repaired, but the relationship between the contractor and the supplier was beyond repair. On 3 May 2021, the contractor held the supplier liable. In court, the contractor claimed payment of more than €36,000 in compensation for the damage he had suffered. He also stated that he had reported the cracking in the façade system to the supplier in 2019. In addition, this had been a pilot project for both parties, and he had started using the façade insulation system on the supplier’s express recommendation. He had followed the supplier’s installation instructions closely. In the contractor’s view, the manufacturer had provided no evidence whatsoever that the façade system had been installed incorrectly, and the supplier had wrongly hidden behind the manufacturer. The supplier disputed the contractor’s claims and denied all liability. According to the supplier, the contractor could no longer rely on an alleged defect in the façade system because he had failed to notify the supplier of it within a reasonable time after discovering it, or when he should reasonably have discovered it. 

The court held that the contractor had failed to complain within a reasonable time, as required by Article 6:89 of the Dutch Civil Code, and that the claim for damages therefore had to be dismissed. It was established that the TBA report was shared with the supplier on 6 February 2020. This was the first time the supplier had received specific notice of the complaint, and it was only a year and a half after the contractor had become aware of the cracking in the external façades. It was also not established that the problems had not been caused by the contractor’s faulty workmanship. Since the contractor had repaired the façades himself, an independent expert could no longer investigate them. Finally, the contractor had failed to substantiate the damage he claimed, providing only an invoice he had drawn up himself, a financial statement and a quotation from the plasterer. No proof of payment was provided. The court dismissed the contractor’s claims.

The contractor may have resolved his client’s façade problems, but unfortunately he failed to assess the growing tensions in his relationship with the supplier. It is not only the installation instructions for the façade system that must be followed, but also the legal rules. The advice: make your complaint in good time! Who knows how things might have turned out for the contractor. Want to avoid regretting your façade choices? Take a look at the members of VMRG, who will be happy to advise you! 

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeAn energy-efficient and comfortable building envelope
  • SubjectVMRG
Share this article

Follow Gevelbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.